RE: [gmf-dev] M4 Milestone Update Proposal

Hi Fred,

 

This seems to be fine, as the tooling side will just wrap up new features before year’s end.  I’ll update the web page and project status log with the new date for M4 as Jan 13, 2006.

 

This does put us in violation of the “train” agreement of releasing +2 weeks after the Platform, but I think the circumstances justify it (besides, we have no dependent projects… yet).

 

Thanks,

Rich

 


From: gmf-dev-bounces@xxxxxxxxxxx [mailto:gmf-dev-bounces@xxxxxxxxxxx] On Behalf Of Frederic Plante
Sent: Tuesday, October 18, 2005 5:39 PM
To: GMF Project developer discussions.
Subject: RE: [gmf-dev] M4 Milestone Update Proposal

 


Oops... I was not aware of this, sorry guys.

Something to consider is that although the proposed extended iteration does not improve the half-staffed end-of-iteration situation, it at least gives a true 6w iteration for members of all geographies.

       - Fred

_________________________________
Frédéric Plante
Rational Software, IBM Software Group
770 Palladium Drive, Ottawa, ON, Canada
tel: (613) 591-7034



"Richard Gronback" <Richard.Gronback@xxxxxxxxxxx>
Sent by: gmf-dev-bounces@xxxxxxxxxxx

10/18/2005 07:31 PM

Please respond to
"GMF Project developer discussions."

To

"GMF Project developer discussions." <gmf-dev@xxxxxxxxxxx>

cc

 

Subject

RE: [gmf-dev] M4 Milestone Update Proposal

 

 

 




Hi Fred,
 
Russian holidays occur in early-mid January, so I’m not sure this makes it any better from the tooling side.  So, let’s get some feedback from the team… thoughts?
 
Thanks,
Rich
 

 



From: gmf-dev-bounces@xxxxxxxxxxx [mailto:gmf-dev-bounces@xxxxxxxxxxx] On Behalf Of Frederic Plante
Sent:
Tuesday, October 18, 2005 3:21 PM
To:
GMF Project developer discussions.
Subject:
[gmf-dev] M4 Milestone Update Proposal

 

Hi Rich,


Because we don't expect many people to be around stabilizing M4 during the last two weeks of the year, I would like to propose an exception to our usual Eclipse +2w pattern by moving the milestone date two weeks later. The proposed M4 would be Jan 13th 2006.


   Thanks

      - Fred

_________________________________
Frédéric Plante
Rational Software, IBM Software Group
770 Palladium Drive, Ottawa, ON, Canada
tel: (613) 591-7034
_______________________________________________
gmf-dev mailing list
gmf-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/gmf-dev


Back to the top