RE: [gmf-dev] M4 Milestone Update Proposal


Oops... I was not aware of this, sorry guys.

Something to consider is that although the proposed extended iteration does not improve the half-staffed end-of-iteration situation, it at least gives a true 6w iteration for members of all geographies.

       - Fred

_________________________________
Frédéric Plante
Rational Software, IBM Software Group
770 Palladium Drive, Ottawa, ON, Canada
tel: (613) 591-7034




"Richard Gronback" <Richard.Gronback@xxxxxxxxxxx>
Sent by: gmf-dev-bounces@xxxxxxxxxxx

10/18/2005 07:31 PM

Please respond to
"GMF Project developer discussions."

To
"GMF Project developer discussions." <gmf-dev@xxxxxxxxxxx>
cc
Subject
RE: [gmf-dev] M4 Milestone Update Proposal





Hi Fred,
 
Russian holidays occur in early-mid January, so I’m not sure this makes it any better from the tooling side.  So, let’s get some feedback from the team… thoughts?
 
Thanks,
Rich
 



From: gmf-dev-bounces@xxxxxxxxxxx [mailto:gmf-dev-bounces@xxxxxxxxxxx] On Behalf Of Frederic Plante
Sent:
Tuesday, October 18, 2005 3:21 PM
To:
GMF Project developer discussions.
Subject:
[gmf-dev] M4 Milestone Update Proposal

 

Hi Rich,


Because we don't expect many people to be around stabilizing M4 during the last two weeks of the year, I would like to propose an exception to our usual Eclipse +2w pattern by moving the milestone date two weeks later. The proposed M4 would be Jan 13th 2006.


   Thanks

      - Fred

_________________________________
Frédéric Plante
Rational Software, IBM Software Group
770 Palladium Drive, Ottawa, ON, Canada
tel: (613) 591-7034