Re: [eclipse-dev] Outage Notice - Saturday, March 26th 2005


I second this concern.  As I read this, CVS and mail (e.g., bugzilla notifications) will be down.  Basically all work will stop since the final days of M6 is all about bugs and committing that last bit of code.  Defering for one week would certainly be prudent.

Jeff



Douglas Pollock <douglas.pollock@xxxxxxxx>
Sent by: eclipse-dev-admin@xxxxxxxxxxx

03/21/2005 05:58 PM

Please respond to
eclipse-dev

To
eclipse-dev@xxxxxxxxxxx
cc
webmaster@xxxxxxxxxxx
Subject
Re: [eclipse-dev] Outage Notice - Saturday, March 26th 2005





On Monday March 21 2005 03:56 pm, Eclipse WebMaster (Denis Roy) wrote:
> I will be migration the dev.eclipse.org server this Saturday, March 26th
> to our new hardware infrastructure. During this time, the CVS
> repositories as well as any mail-related resources will be unavailable.

I have some concerns about the selected date.  Would it be possible to delay
the migration until after 3.1 M6 ships?

3.1 M6 is imminent, and represents an API freeze.  Removing access to the CVS
servers for 24 hours could hinder people who are trying to complete changes
in time for the API freeze.

Also, there were some unexpected difficulties when trying to complete the
phase one migration.  If similar difficulties were to occur during the
milestone week, this could causes delays or frustrations in trying to
complete 3.1 M6 on time.



cheers,
d.
_______________________________________________
eclipse-dev mailing list
eclipse-dev@xxxxxxxxxxx
To change your delivery options, retrieve your password, or unsubscribe from this list, visit
http://dev.eclipse.org/mailman/listinfo/eclipse-dev


Back to the top