[dsdp-tm-dev] Revised TM Project Plan
|
Hello,
as agreed in the TM phone call last week, I have revised the TM
Project plan as follows:
* Removed M0 milestone to account for what really happened
* Adapted M1 content to account for what really happened
* Moved goals missed in M1 to M2
* Moved "user actions", "import/export", from M2 to M3
* Added "update site" for M3
* Added tasks required to meet Eclipse Quality for Release Review:
- Create Junit test suites for all API
- Get rid of Platform internal package access where possible
The draft plan is accessible at
http://www.eclipse.org/dsdp/tm/development/draft-plan.php
Please review this draft carefully and let me know of any
modifications you would like to make, before I make it
official.
In particular, I'd like to know if you find the goals realistic
or we should make further modifications to dates and/or content.
As per the DSDP/Standard Charter, "the development plan must be
approved by a majority of Committers of the Project".
Thanks,
Martin
--
---------------------------------/()\-----------------------------------
Dipl.-Ing. Martin Oberhuber mailto:martin.oberhuber@xxxxxxxxxxxxx
Member of Technical Staff Phone (UTC +1h): +43 (662) 457915-85
Wind River Systems (Salzburg) GmbH Fax: +43 (662) 457915-6
Jakob-Haringer-Str.8, A-5020 Salzburg, Austria http://www.windriver.com
----------------------- How Smart Things Think -------------------------