RE: [dsdp-tm-dev] Revised TM Project Plan

Hello again,

I've discussed the draft TM project plan revision with
Dave Dykstal today, and we see some risks with achieving 
it:

1.) Our slow start due to IP Review has considerably 
    shortened the time we had planned for API Review
    before we can freeze it.
2.) Additional requirements we have found for Release
    Review processes force us to calculate enough time
    for the "endgame" before we can declare our release.

The options we see to address these issues include
 - Not making a 1.0 release but a 0.xx and remaining
   in Incubation phase. Looks not like a good option
   to us, but we'd like to have this discussed in public.

 - Adding another milestone before our release (M5),
   and moving the API freeze from M3 to M4. This 
   would give us more time for API lock-down and review,
   but would also delay the release date by at least 4 weeks
   (if we tighten the schedule for release candidates).

Dave Dykstal will come up with a detailed proposal of
how planned features can be rearranged to accommodate
the additional milestone.

We hate proposing a change in schedule, but we think
it's better to plan doing so early and then sticking
to the revised schedule.

Please let us know your comments.

Thanks,
Martin
--
Martin Oberhuber - WindRiver, Austria
+43(662)457915-85
 

> -----Original Message-----
> From: dsdp-tm-dev-bounces@xxxxxxxxxxx 
> [mailto:dsdp-tm-dev-bounces@xxxxxxxxxxx] On Behalf Of 
> Oberhuber, Martin
> Sent: Thursday, May 11, 2006 3:28 PM
> To: Target Management developer discussions
> Subject: [dsdp-tm-dev] Revised TM Project Plan
> Importance: High
> 
> Hello,
> 
> as agreed in the TM phone call last week, I have revised the TM
> Project plan as follows:
> 
> * Removed M0 milestone to account for what really happened
> * Adapted M1 content to account for what really happened
> * Moved goals missed in M1 to M2
> * Moved "user actions", "import/export", from M2 to M3
> * Added "update site" for M3
> * Added tasks required to meet Eclipse Quality for Release Review:
>   - Create Junit test suites for all API
>   - Get rid of Platform internal package access where possible
> 
> The draft plan is accessible at
> http://www.eclipse.org/dsdp/tm/development/draft-plan.php
> 
> Please review this draft carefully and let me know of any
> modifications you would like to make, before I make it 
> official.
> 
> In particular, I'd like to know if you find the goals realistic
> or we should make further modifications to dates and/or content.
> As per the DSDP/Standard Charter, "the development plan must be 
> approved by a majority of Committers of the Project".
> 
> Thanks,
> Martin
> 
> --
> ---------------------------------/()\-------------------------
> ----------
> Dipl.-Ing. Martin Oberhuber        
> mailto:martin.oberhuber@xxxxxxxxxxxxx
> Member of Technical Staff          Phone  (UTC +1h): +43 
> (662) 457915-85
> Wind River Systems (Salzburg) GmbH              Fax: +43 
> (662) 457915-6
> Jakob-Haringer-Str.8, A-5020 Salzburg, Austria  
> http://www.windriver.com
> ----------------------- How Smart Things Think 
> -------------------------
>  
> _______________________________________________
> dsdp-tm-dev mailing list
> dsdp-tm-dev@xxxxxxxxxxx
> https://dev.eclipse.org/mailman/listinfo/dsdp-tm-dev
> 


Back to the top