Re: [bpel-dev] completion timeframe for reconciliation work?

Hi David,

I'm currently working on reconciliation stuff so I just can't pass by :)

The reconciliation is approximately 60% complete (based on class count
in BPEL model impl) and last two weeks I was pretty much concentrated
on fixing bugs and not increasing progress to improve stability.
Currently I'm looking on FaultHandler issue
(http://dev.eclipse.org/mhonarc/lists/bpel-dev/msg00590.html) and
would be very glad if you can provide any help. As soon as I finish
this I'll continue implementing reconciliation for other model items.

As for the time estimation my pessimistic estimation is the end of
Novemer, but I think it'll be ready earlier, because all necessary
algorithms are already implemented and mostly that's just routine
operations of putting update code in place. But exceptions happen and
sometimes they're quite difficult to solve.

Thanks,
Dennis

2007/10/30, David Black <david.black@xxxxxxxxxxxxx>:
> Hi,
>
> Apologies if this question has been asked/answered before.
>
> Is there a timeframe for completion of the DOM/EMF reconiliation work? I'm
> looking at the milestone plan, specifically M4 and there was a tentative
> date of Sep 30, 2007 .
>
> thanks
> David Black
>
> ---------------------------------------
> David Black
> Cape Clear Software
>
> office: +353 1 2419952
> email:  david.black@xxxxxxxxxxxxx
> skype:  david.black
> msn:    dblack@xxxxxxxxxxxx
>
> No virus found in this outgoing message.
> Checked by AVG Free Edition.
> Version: 7.5.503 / Virus Database: 269.15.12/1098 - Release Date: 10/29/2007
> 9:28 AM
>
>