Re: [aperi-dev] Please review'Aperi IntegratedDevelopment VerificationTest Plan' based on Aperi Roadmap V7

>>> On Thu, Nov 1, 2007 at 11:09 AM, in message
<OF452A014A.2D15466B-ON85257386.005CA302-88257386.005E2750@xxxxxxxxxx>, Hans
Lin <linh@xxxxxxxxxx> wrote: 
> Hi Robert,  Thanks for the info regarding the OS level needed to operate

Hi Hans,

> Xen- based virtual machine.  At the meantime,  Aperi IDVT team does need
> your help to do the regression tests on the Xen machine for the final R0.4
> milestone build which is due at 11/19/2007 and we have two weeks
> (11/30/2007)  to finish
> the regression tests.

Okay, I'll plan for that.