Bug 2092 - [Tasks] New task may be filtered out (1GE5PP6)
Summary: [Tasks] New task may be filtered out (1GE5PP6)
Status: RESOLVED FIXED
Alias: None
Product: Platform
Classification: Eclipse Project
Component: UI (show other bugs)
Version: 2.0   Edit
Hardware: All Windows 2000
: P3 normal (vote)
Target Milestone: ---   Edit
Assignee: Chris McLaren CLA
QA Contact:
URL:
Whiteboard:
Keywords: investigate, usability
Depends on:
Blocks:
 
Reported: 2001-10-10 22:26 EDT by Kevin Haaland CLA
Modified: 2002-09-05 12:03 EDT (History)
0 users

See Also:


Attachments

Note You need to log in before you can comment on or make changes to this bug.
Description Kevin Haaland CLA 2001-10-10 22:26:18 EDT
Set the task filter to be "Where task priority is" "high" only.
	Create a new task.
	New task is not visible. Should be, you haven't assigned a priority to this new task yet.

NOTES:
	EJP (7/30/01 10:15:28 AM)
		We could open a dialog telling the user that the task will be filtered and will not
		be showed in the task list. The dialog could have a "Do not show this message again" check box.
Comment 1 DJ Houghton CLA 2001-10-29 17:50:53 EST
PRODUCT VERSION:
	109

Comment 2 Kevin Haaland CLA 2002-01-21 20:31:00 EST
Defer
Comment 3 Randy Giffen CLA 2002-08-07 11:09:33 EDT
Reopen for investigation
Comment 4 Chris McLaren CLA 2002-09-05 12:03:38 EDT
fixed in 2.0