[platform-releng-dev] 3.1 M6 Build schedule


Please note that the 3.1 M6 warm up build will be on Thursday March 24 instead of the usual Monday.  This Friday is a holiday in North America and the following Monday is a holiday in Europe.

Thursday Mar 24 08:00 EST - 3.1 M6 Warm-up build
- this is just a warm up
- rebuilds will only be run if there are compile errors, missing plug-ins or the build is unusable.  (Same as the integration build rebuild policy)

Tuesday, Mar 29 - 3.1 M6 Test Candidate build

- 3.1 M6 build toward Test candidate at 12:10 am, 8 am, noon, 4 pm, and 8 pm builds if map files are updated
- Midnight Integration builds will be in lieu of the nightly builds on Tuesday and Thursday.
- goal: a good build for the test pass on Wednesday

-The last chance to submit to the test candidate will be the Tuesday 8pm build

Wednesday, Mar 30 (all day) - 3.1 M6 Test pass

  - intensive 1-day test pass on 3.1 M6 candidate

Thursday, Mar 31 - Build toward Milestone candidate

-3.1 M6 build toward Milestone candidate with 12:10 am, 8 am, noon, 4 pm, and 8 pm builds if map files are updated
- for a rebuild, only team(s) requesting the rebuild need to recheck and sign off (although they may request other teams to revalidate potentially affected functionality)
- goal: a milestone candidate for Friday

Friday, Apr 1

-Final sanity check, all teams sign off, 3.1 M6 is released.

A summary of the schedule is available here...

http://dev.eclipse.org/viewcvs/index.cgi/%7Echeckout%7E/platform-releng-home/buildSchedule.html


Please note that performance tests will only be run on the first build of the day due to the time that they take to complete.


Kim