Hi,
Kepler release date, which is also MAT 1.3.0 release date, is approaching.
Next week the Kepler RC1 will be produced. My intention is to try to provide the
final MAT contribution to Kepler already with RC1, just to avoid the stress and risk of contributing to the latest RCs. In case of critical issues, we can of course take part in the next RCs.
Current status:
-
IP Log – submitted today
-
Release Review documentation – It is in the PMI tool, not yet sent for approval to the PMC (see my previous mail on the list). I’ll wait for the IP log approval before I ask the PMC
-
New & Noteworthy – Andrew helped me to compile the new and noteworthy document. The documentation of the last snapshot build contains it. Let me know if I missed something
What is next?
-
Some last tests – if you are interested, just try the latest snapshot version[1] and let us know if there are some critical issues with it
-
I will build a version about noon (CET) which I hope will be the final version. As mentioned above – in case of issues we’ll produce another one
Krum