Hi,

Things are coming along for our 0.3 release.  I've completed the
majority of the docuware (see [1] if you're interested).  We're
tentatively scheduled for a review call on Wednesday August 12th.

Remaining items:

- get SystemTap GUI stuff into build (Anithra and Phil have been looking
  at this)
- remove GProf stuff from build (Xavier is on vacation and I think it's
  best that we postpone and ensure it's all ready to go.  0.4 is only 8
  weeks away -- I promise it'll only be 8 weeks this time :)
- prepare N&N (sections assigned to everyone)

The tracking bug for our 0.3 release is:

285202: Prepare 0.3 Release
https://bugs.eclipse.org/bugs/show_bug.cgi?id=285202

Everyone, please take a look at open bugs that have a 0.3 target
milestone and provide an update on the bug and/or postpone them until
0.4.  There are over 20 of them :)

https://bugs.eclipse.org/bugs/buglist.cgi?query_format=advanced&short_desc_type=allwordssubstr&short_desc=&classification=Technology&product=Linux+Tools&target_milestone=0.3&long_desc_type=allwordssubstr&long_desc=&bug_file_loc_type=allwordssubstr&bug_file_loc=&status_whiteboard_type=allwordssubstr&status_whiteboard=&keywords_type=allwords&keywords=&bug_status=UNCONFIRMED&bug_status=NEW&bug_status=ASSIGNED&bug_status=REOPENED&emailtype1=substring&email1=&emailtype2=substring&email2=&bugidtype=include&bug_id=&votes=&chfieldfrom=&chfieldto=Now&chfieldvalue=&cmdtype=doit&order=Reuse+same+sort+as+last+time&field0-0-0=noop&type0-0-0=noop&value0-0-0=

Once we have a candidate build, I'll ask everyone to do some final
testing.

Thanks,

Andrew