RE: [epf-dev] IMPORTANT - OpenUP/Basic: due work and planned work

Ricardo, since I haven't been versed in the where and whyfores of CVS, here
are some things that should be added to the list of OpenUP process elements,
as it relates to Project Management...
 
Checklist: Iteration Plan	
Checklist: Project Plan	
Concept: Phase (in base_concepts)
Concept: Risk
Example: Project Plan
Example: Iteration Plan
Example: Work Items List
Guideline: Project Plan

In that spreadsheet, I might suggest putting templates inline with each
discipline instead of a separate section (#7)...

I've just finished putting all the PM-related bugs (and some extras -- looks
like I added about 65 or so new items) in Bugzilla and it would be nice if
one could specify the discipline/domain as a part of the component (instead
of all items going into the "content" bucket). Like others, I'm using a
prefix (such as "PM") in the summary...

Also, I struggled with how to set bug attributes like priority and severity,
so I just took a stab at it... If you have any suggestions, let me know...

Thanks, Chris ~:|

________________________________

From: epf-dev-bounces@xxxxxxxxxxx [mailto:epf-dev-bounces@xxxxxxxxxxx] On
Behalf Of Ricardo Balduino
Sent: Monday, June 05, 2006 2:42 PM
To: epf-dev@xxxxxxxxxxx
Subject: [epf-dev] IMPORTANT - OpenUP/Basic: due work and planned work
Importance: High



Dear committers, 

We have important actions to take for OpenUP/Basic, please run the report at
the bottom of this email, so you can have the data at hand: 

- M2: There is still one open issue related to M2 - we need closure on this
asap. 
- M3: There are 5 issues. 
        - 2 are resolved, waiting to be closed 
        - 1 is assigned, should be resolved 
        - 2 are new, not even assigned to anyone 
- M4: From the 45 issues planned for M4, 31 haven't been assigned to anyone.

        - Package owners, if you have added entries, please revisit them to
assign to interested contributors. In case you haven't added entries for
your package, please do so (yes, this number will be increased). 
        - Community, all contribution is welcome :-) 

As you can see, we have a good volume of entries in Bugzilla that need
action (some due for M2 and M3, but most are planned for M4). Taking this
action early in M4 will help us to address the objectives for this
milestone. 

I'm also attaching 4 spreadsheets created by Chris Sibbald (thanks Chris)
that list all elements in need of content to be written. It is certainly
useful information for package owners to check completeness of their
packages. 

Link to the report: 

https://bugs.eclipse.org/bugs/report.cgi?x_axis_field=priority&y_axis_field=
assigned_to&z_axis_field=target_milestone&query_format=report-table&short_de
sc_type=allwordssubstr&short_desc=&classification=Technology&product=EPF&com
ponent=Content&version=1.0&target_milestone=1.0+M2&target_milestone=1.0+M3&t
arget_milestone=1.0+M4&target_milestone=1.0+M5&long_desc_type=allwordssubstr
&long_desc=&bug_file_loc_type=allwordssubstr&bug_file_loc=&status_whiteboard
_type=allwordssubstr&status_whiteboard=&keywords_type=allwords&keywords=&bug
_status=NEW&bug_status=ASSIGNED&bug_status=REOPENED&bug_status=RESOLVED&bug_
status=VERIFIED&emailtype1=substring&email1=&emailtype2=substring&email2=&bu
gidtype=include&bug_id=&votes=&chfieldfrom=&chfieldto=Now&chfieldvalue=&form
at=table&action=wrap&field0-0-0=noop&a!
mp;a!%20mp;type0-0-0=noop&value0-0-0= 

Please, don't hesitate to contact me (and this list) if you have any
question or comment. 
Thank you, 

Ricardo Balduino