Jonah,
That ends way too close to Christmas. I think we should change
it immediately. No one will want to deal with urgent issues that
late into December...
Regards,
Ed
On 23/09/2021 20:07, Jonah Graham
wrote:
Hi folks,
I am preparing/scheduling my work for 2021-12 release cycle
and I found the dates were not what I expected/remembered.
We don't seem to have written down a final decision on this
discussion item anywhere[1] and it was on the agenda for
Feb 2021 meeting[2]. The current 2021-12 schedule shows
classic pattern[3], rather than the shortened version that
releases on Dec 8.
Did we decide to keep the classic pattern at that Feb
meeting, or was there an update to [3] that should have been
done to reflect the proposal in [1].
If we did decide to do the new proposal, is it too late to
update[3]?
(My vote is if we did agree in Feb 2021 to shorten M1, that
we update [3] now)
Thanks
Jonah
Hi
all,
Le 06/01/2021 à 16:49, Jonah Graham a écrit :
> Thanks folks for the discussion this morning/afternoon.
>
> As mentioned in the meeting we will continue this
discussion once we
> have dates.
I prepared the schedule for 2021-06, 2021-09 and 2021-12.
Please review it on the wiki and confirm that it is okay for
you by
answering to this email:
* https://wiki.eclipse.org/Category:SimRel-2021-06
* https://wiki.eclipse.org/Category:SimRel-2021-09
* https://wiki.eclipse.org/Category:SimRel-2021-12
For the 2021-12, if we follow the classical pattern we will
have mostly
the same release date as the one this year.
If we would like to have one week between the GA and the
holidays, we
can reduce M1 dev period for this release by one week and then
release
on December 8th.
2021-12 M1 Friday, October 08, 2021 10/01 to
10/08
*2 weeks from 2021-09 GA*
2021-12 M2 Friday, November 5, 2021 10/22 to
10/29 3 weeks from M1
2021-12 M3 Friday, November 19, 2021 11/12 to
11/19
3 weeks from M2
2021-12 RC1 Friday, November 26, 2021 11/19 to
11/26
1 week from M3
2021-12 RC2 Friday, December 3, 2021 11/26 to
12/03 1 week from RC1
Quiet period 12/03 to 12/07
2021-12 GA Wednesday, December 8, 2021
5 days from RC2
What do you think?
Best regards,
--
Mélanie Bats
CTO
+33 7 87 69 42 84
+33 5 34 57 16 29
@melaniebats
*Obeo*
25 Boulevard Victor Hugo - Colomiers - France
http://www.obeo.fr
_______________________________________________
eclipse.org-planning-council mailing list
eclipse.org-planning-council@xxxxxxxxxxx
To unsubscribe from this list, visit https://www.eclipse.org/mailman/listinfo/eclipse.org-planning-council
_______________________________________________
eclipse.org-planning-council mailing list
eclipse.org-planning-council@xxxxxxxxxxx
To unsubscribe from this list, visit https://www.eclipse.org/mailman/listinfo/eclipse.org-planning-council