Phillipe,
Is this on the wiki somewhere so that the team can start planning the
Io/Titan/whatever release around it? I searched for it, but the wiki
search is sometimes not as good as Google has trained us all to expect.
- Bjorn
Here it is again (take 3), with fix for a missing week in M7.
Allocated one more week in M7 to compensate for EclipseCon distraction.
M1 - August 8, 2008 (6 weeks)
>>> (3.4.1/Ganymede-SR1 +0 dates: RC1-September 1, RC2-September 8,
RC3-September 15)
M2 - September 19, 2008 (6 weeks) - PLANNING
M3 - October 31, 2008 (6 weeks) - DEV
M4 - December 12, 2008 (6 weeks) - DEV
M5 - January 30, 2009 (7 weeks) - MAJOR FEATURE WORK COMPLETED
>>> (3.4.2/Ganymede-SR2 +0 dates: RC1-February 2, RC2-February 9,
RC3-February 16)
M6 - March 13, 2009 (6 weeks) - API FREEZE, FEATURE TUNING, I18N &
ACCESSIBILITY
>>> (EclipseCon March 23-27)
M7 - May 1st, 2009 (7 weeks) - PERFORMANCE & POLISH, BEST EFFORT ON DOC
RC1 (2 weeks) - May 15, 2009
RC2 (1 week) - May 22, 2009
RC3 (1 week) - May 29, 2009
RC4 (1 week) - June 5, 2009
--
[end of message]
------------------------------------------------------------------------
_______________________________________________
eclipse.org-planning-council mailing list
eclipse.org-planning-council@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/eclipse.org-planning-council
IMPORTANT: Membership in this list is generated by processes internal to the Eclipse Foundation. To be permanently removed from this list, you must contact emo@xxxxxxxxxxx to request removal.