Here it is again (take 3), with fix
for a missing week in M7. Allocated one more week in M7 to compensate
for
EclipseCon distraction.
M1 - August 8, 2008 (6 weeks)
>>> (3.4.1/Ganymede-SR1
+0 dates: RC1-September 1, RC2-September 8, RC3-September 15)
M2 - September 19, 2008 (6 weeks) -
PLANNING
M3 - October 31, 2008 (6 weeks) - DEV
M4 - December 12, 2008 (6 weeks) -
DEV
M5 - January 30, 2009 (7 weeks) -
MAJOR
FEATURE WORK COMPLETED
>>> (3.4.2/Ganymede-SR2
+0 dates: RC1-February 2, RC2-February 9, RC3-February 16)
M6 - March 13, 2009 (6 weeks) - API
FREEZE, FEATURE TUNING, I18N & ACCESSIBILITY
>>> (EclipseCon March
23-27)
M7 - May 1st, 2009 (7 weeks) -
PERFORMANCE
& POLISH, BEST EFFORT ON DOC
RC1 (2 weeks) - May 15, 2009
RC2 (1 week) - May 22, 2009
RC3 (1 week) - May 29, 2009