Re: [eclipse.org-planning-council] [cross-project-issues-dev] Staging the next iteration (whatever it is named)

Phillipe,
Is this on the wiki somewhere so that the team can start planning the Io/Titan/whatever release around it? I searched for it, but the wiki search is sometimes not as good as Google has trained us all to expect.

- Bjorn

Here it is again (take 3), with fix for a missing week in M7. Allocated one more week in M7 to compensate for EclipseCon distraction.

M1 - August 8, 2008 (6 weeks)
>>>  (3.4.1/Ganymede-SR1 +0 dates:  RC1-September 1, RC2-September 8, RC3-September 15)
M2 - September 19, 2008 (6 weeks) - PLANNING
M3 - October 31, 2008 (6 weeks) - DEV
M4 - December 12, 2008 (6 weeks) - DEV
M5 - January 30, 2009 (7 weeks) - MAJOR FEATURE WORK COMPLETED
>>>  (3.4.2/Ganymede-SR2 +0 dates:  RC1-February 2, RC2-February 9, RC3-February 16)
M6 - March 13, 2009 (6 weeks) - API FREEZE, FEATURE TUNING, I18N & ACCESSIBILITY
>>>  (EclipseCon March 23-27)
M7 - May 1st, 2009 (7 weeks) - PERFORMANCE & POLISH, BEST EFFORT ON DOC
RC1 (2 weeks) - May 15, 2009
RC2 (1 week) - May 22, 2009
RC3 (1 week) - May 29, 2009
RC4 (1 week) - June 5, 2009

--

[end of message]