[cosmos-dev] Committers/contributors should know: how-to for the remainder of v1.1 iteration 1

Hi folks,

This is the last week of development for iteration 1. On Wednesday we will 
build a candidate build and every team must run a sanity test on this 
driver to ensure that everything that you've checked in so far is good for 
the official test pass, which starts Monday next week. Due to the 
holidays, the test pass for iteration 1 will span 3 weeks instead of the 
standard 2 weeks (Dec 22 to Jan 09).

Each team must state the results of its tests this week in the wiki page 
showing this week's test state: http://wiki.eclipse.org/COSMOS_v1.1_I1w5 
Only when all teams have reported status will we know if we're good to go 
with the test pass or not.

All status during the test pass of iteration 1 must be entered in this 
wiki page: http://wiki.eclipse.org/COSMOS_v1.1_I1_Test

This iteration we are producing an iteration driver, not a milestone 
driver, and thus the test pass is to ensure that the iteration driver is 
stable. We will not advertise this driver because Eclipse allows us to 
advertise only Milestone and Release drivers, but it is possible that an 
early adopter will pick up this driver and it is expected, in accordance 
with Agile practices, that the driver is usable.

You can find links to all of the iteration plans and test pages in the 
COSMOS Release Plan: http://wiki.eclipse.org/Cosmos_Release_Plan#Features

MILESTONE               DURATION   START DATE    END DATE DESCRIPTION
Iteration 1             8 weeks    Nov-17-2009   Jan-09-2009 Enhancements  

   i1 Development       5 weeks    Nov-17-2009   Dec-19-2009 Development & 
bug fixes
   i1 Testing           3 weeks    Dec-22-2009   Jan-09-2009 Validation 
Testing 

Iteration 2             6 weeks    Jan-12-2009   Feb-20-2009 Enhancements  

   i2 Development       4 weeks    Jan-12-2009   Feb-06-2009 Development & 
bug fixes 
   i2 Testing           2 weeks    Feb-09-2009   Feb-20-2009 Validation 
Testing 

Iteration 3             6 weeks    Feb-23-3009   Apr-03-2009 Stabilize 
   i3 Development       4 weeks    Feb-23-2009   Mar-20-2009 Development & 
bug fixes 
   i3 Testing           2 weeks    Mar-23-2009   Apr-03-2009 Validation 
Testing 

Milestone driver        1 day        Apr-03-2009         Apr-03-2009 
Available for POCs 

Iteration 4             6 weeks    Apr-06-2009   May-15-2009 Enhancements  

   i4 Development       4 weeks    Apr-06-2009   May-01-2009 Development & 
bug fixes 
   i4 Testing           2 weeks    May-04-2009   May-15-2009 Validation 
Testing 

Iteration 5             6 weeks    May-18-2009   June-26-2009 Stabilize  
   i5 Development       4 weeks    May-18-2009   June-12-2009 Development 
& bug fixes 
   i5 Testing           2 weeks    June-15-2009  June-26-2009 Validation 
Testing 

COSMOS 1.1 availability 1 day      June-26-2009  June-26-2009     GA 
Release 


Ruth Lee
IBM Toronto Lab
ruthdaly@xxxxxxxxxx