Re: [cdt-dev] Progressing towards 2.0 GA

Just a quick correction, the platform RC4 build is planned for Friday 
morning, not mid week.

Doug Schaefer, IBM's Eclipse CDT Architect
Ottawa (Palladium), Ontario, Canada



Kleanthis Hapitas/Ottawa/IBM@IBMCA 
Sent by: cdt-dev-admin@xxxxxxxxxxx
06/22/2004 12:01 PM
Please respond to
cdt-dev


To
cdt-dev@xxxxxxxxxxx
cc

Subject
[cdt-dev] Progressing towards 2.0 GA







Hi all, 

I thought we should go around and see how we are progressing towards the 
GA milestone targeted for the end of the month. 

The Eclipse platform declared RC3 just this past weekend, and they have 
identified about 25 defects that they will still want to fix before going 
GA. So, they are planning to have RC4 built by the middle of this week, 
and once those 25 fixes have been tested and verified, and assuming no 
further regressions, they will announce GA likely before the end of this 
week (June 25). 

Given that Eclipse will be done by June 25, we should think about drawing 
a line for when the CDT could build our (first) release candidate. Once we 
do that, the goal would be that everyone takes a good look at the build to 
make sure we have no further show stoppers. If we don't we could declare 
GA after a few days of soak. If we do, we would do another release 
candidate build, and so on... 

So, what say you? What's a reasonable target for an initial release 
candidate? End of the week? Early next week? 

Cheers, 

Kleo Hapitas 