Re: [bpel-dev] the project milestone plan and buglist updates

Vitaly,

Welcome.

I was twice in St. Petersburg, but at that time it was called something different :-)


Tishkov, Vitaly V wrote:

Hi,

 

1. I’ve found that the project plan is a bit outdated. Are there plans to update the plan? J

There are plans to update the plans. These are known knowns :-)

Regarding the source editor view, Roman said you were very close to getting this done ... is it really true ? It's one of our post 1.0 items, but if you are very close we can certainly try pushing it as a target for say M4 (as M3 is almost out).

 

2. A few bugs from the bugzilla look having outdated status too. E.g. these bugs look fixed but they are marked as new:

            - https://bugs.eclipse.org/bugs/show_bug.cgi?id=119977

            - https://bugs.eclipse.org/bugs/show_bug.cgi?id=119892

            - https://bugs.eclipse.org/bugs/show_bug.cgi?id=120171

(may be there are more, these are just the ones I noticed quickly).

I can volunteer to review the full list of bugs and mark fixed bugs as fixed. Is it desirable?

That is fine. We all were supposed to go through them and mark some bugs as closed. If you have enough visibility into the source code that you can make that call then please do. If you are uncertain, then please don't touch it. If you can send this list of which ones you had closed that would nice too ...

Best,

-m

 

Thanks,

            Vitaly.

 

 


_______________________________________________ bpel-dev mailing list bpel-dev@xxxxxxxxxxx https://dev.eclipse.org/mailman/listinfo/bpel-dev


-- 
Michal Chmielewski, CMTS, Oracle Corp, 
W:650-506-5952 / M:408-209-9321 

"Manuals ?! What manuals ? Son, it's Unix, you just gotta know." 

Back to the top