We'll use this bug to track the release We require IP Team approval of the IP Log. We require PMC approval of the release and review materials.
I've rescheduled this review to take place September 20, 107.
Hi project team, are you still planning on releasing for September 20, 2017?
Hi Stephanie, no, we are currently aiming for end of November.
(In reply to Olaf Bergmann from comment #3) > Hi Stephanie, > > no, we are currently aiming for end of November. Hi Olaf, sounds good. I've changed the release review date to November 15th, if that is too early in the month, our next available release review date will be December 6, 2017. Please let me know which works better for you. Thanks, Stephanie
Hi project team, are you still planning on releasing in November? If so, will you be ready for November 15th?
November 15th will be tough to meet. End of November or December will be more realistic.
Thanks Olaf, keep us posted! We will keep our eye on December 6th for now.
Hi Olaf, just a reminder that December 6th is rapidly approaching and we will need all the review materials submitted by November 28th (this coming Tuesday) at the absolute latest to ensure we can get the release approved on December 6th. Though sooner is better.
I'm closing this as WONTFIX. We can reopen when you're ready.