Re: [cross-project-issues-dev] Status and outlook for Kepler M4 +3

Eric Gwin <eric.gwin@xxxxxxxxxx> wrote on 12/20/2012 02:04:11 PM:
>
> No. EclipseLink's M4 was 2.5.0.v20121016-ab08992, it is what was
> included in the aggregation files. However, Dali is including
> EclipseLink directly, and they are using M5 (2.5.0.v20121120-
> ec51fcc). So currently both versions are in the aggregation.
>
> When I released our M5 I thought I had updated the aggregation files
> to reflect the new Milestone. However somehow it never did occur. I
> probably forgot to push my local change, and later issues caused me
> to re-clone so the change was lost.

There is clearly still confusion on dates and milestones. Kepler M5 will be February 8, 2013. See

http://wiki.eclipse.org/Kepler/Simultaneous_Release_Plan#Schedule

John