Friday, I did the first m2e contribution to the aggregator build.On 2010-12-10, at 3:06 PM, David M Williams wrote: Just wanted to remind everyone that with
M4 we move to the "short window", So, today is +0 ... Wednesday
is +3. EPP Packages on Thursday, and make available on Friday, 12/17/2010,
9 AM (Eastern). That's the plan. So we can all have a nice
relaxing holiday.
So, please pay close attention to aggregation
build breaks. I know I will be!
Also, M4 is the deadline for projects
to declare intent, and get into the aggregation build for the common repository.
See http://wiki.eclipse.org/Indigo
for all the common documents and links you'll need to participate.
Especially the requirements document:
http://eclipse.org/indigo/planning/EclipseSimultaneousRelease.php
The requirements document is considered
done, for Indigo. There might be editing for clarity, but the list of requirements
should not change substantially ... and there are only small changes from
last year's list..
The web app that summarizes the metadata
(and the Portal's tracking data entry) is mostly ready. There are some
edits still required there. But should be usable, not lose data, etc.
Start at http://eclipse.org/indigo/planning/SimultaneousReleaseOverview.php
As always, feel free to ask questions.
Here on cross-project list is best.
_______________________________________________ cross-project-issues-dev mailing list cross-project-issues-dev@xxxxxxxxxxx https://dev.eclipse.org/mailman/listinfo/cross-project-issues-dev
|