RE: [cross-project-issues-dev] Proposal for a Callisto RC4a

David,

 

Tomorrow, we plan to start a full test pass with an integration build of TPTP using Eclipse SDK RC7.

 

I don’t have any objection to RC4a proposal.

 

Thanks,

-Sri


From: cross-project-issues-dev-bounces@xxxxxxxxxxx [mailto:cross-project-issues-dev-bounces@xxxxxxxxxxx] On Behalf Of David M Williams
Sent: Monday, June 05, 2006 9:11 AM
To: Cross project issues
Subject: [cross-project-issues-dev] Proposal for a Callisto RC4a

 


We discussed before ... and said "if reason found" we'd re-consider ... and I think there is now reason to promote an RC4a, which is just like RC4, except the base platform would
be moved up to its RC7 level. The main reason, for me, is to pick up the update manager improvements described in bug 144876 ( https://bugs.eclipse.org/bugs/show_bug.cgi?id=144876 ).
Technically speaking, we would not even *have* to re-issue Callisto, if users simply started with the Eclipse SDK RC7, but 1) I would not want to publically encourage this, since
none of the other Callisto projects have had a chance to test, or voice dissent with that plan, and 2) would prefer an orderly official "rollout" to practice good process.

So .. any objections to us providing an RC4a? As detailed below? I think only expectation on projects would be to do some sanity checking to make sure RC7 didn't accidentally introduce some
breaking change ... if it did, of course, we'd really want to know that anyway! ... so, this note is just to give some "fair warning" that this is the plan, and see if anyone objects.
If I hear no objections, I'll assume silence is consent, and prepare this RC4a version. Thanks.

 RC4a (9 -Jun)

    * 7-June - Platform (RC7)
    *  -----  CDT (RC2), DTP(RC4), EMF (RC6a), GEF (RC4), VE (RC2)
    *  -----  BIRT(RC4), GMF (RC4), TPTP (i3), WTP (RC4)
    * 9 -June - admin, mirror propagation
   