Platform ISV Doc Plan

Last updated:  27 May 2002

Content

Priority 1 items

Component Content Status
Team New chapter Outline complete.

Sent to KM 5/22/2002

Product config & install New chapter Outline complete.

Sent to VK 5/23/2002

Debug/Launch New chapter Outline complete.

Sent to DW 5/27/2002

Help Rewrite old chapter to discuss new TOC structure.  Add sections on info pops and active help. In progress.  Working with KH to merge content and create reference material.  Sent proposed outline 5/27/2002
Core Updated features:  project natures (one-of-nature, other changes), project description changes, file modification validator, move/delete hook, derived resources, team private resources Not started.

Consult DJ for review/outline review

Workbench Updated features:  decorators, capabilities Not started.  NE has provided diff list.
SWT Minor revisions, add discussion of FormLayout Not started.
ALL CHAPTERS All chapters should be reviewed by component owners after first pass of edits.

Priority 2 items

Component Content Status
Search/compare framework New chapter Not started.

Schedule

May 13-19 Planning.  Finish overall TOC for updated Developer Guide. 
May 20-26 Finish individual outlines for new chapters and establish reviewer.
May 27-31 Start writing new chapters (VCM, Product configuration, Debug, Help)
June 3-9 Finish new chapters and send for review.
June 10-16 Update Core, SWT, Workbench chapters and send for review.  Review any chapters that were not touched and get component owner review.
June 17-21 Incorporate review feedback, take screen snaps, fix up reference doc pointers and structure.  Search/compare framework chapter/roadmap (time permitting)
June 24 Doc frozen.