[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
|
[news.eclipse.technology.alf] ALF Weekly Project Meeting 02/01/07
|
ALF Weekly Project Meeting
01-Feb-2007
Eclipse Review Process
a.. Brian will be scheduling the review for Milestone .7 for February,
depending on the final analysis by Kim and Summer on the impact of having
the three Cognizant developers taking the week of Christmas off. 01/11/07 -
Brian says this will be a release review. Next week we should be able to
decide when we want to schedule this. Brian will send out some draft slides
and a reminder of the criteria required for this review. 01/29/07 - Brian
has started the process to have this meeting established. There's some
question about whether we can have this since we haven't exited the
incubation phase. Brian is waiting to hear back from Bjorn on this.
Project Schedule
a.. Project schedule reviewed and updated in today's meeting. Latest
versions will be posted to Serena internal Sharepoint site and to the
Eclipse website as well.
Other:
a.. 12/07/06 Brian met with Telelogic this morning to discuss possible
in ALF integrations. No bandwidth, not really interested. Presented
ALF/Applications to the Serena reps to the partners earlier in the week.
Direct presentation to the partners is desirable; Brian will work on setting
that up. 01/11/07 - Some additional meetings are happening. We'd like to
get Telelogic involved in the requirements Vocabulary. Brian has contacted
Kevin Parker and Kelly Shaw about this. 01/18/07 - meeting scheduled for
Friday of next week. 01/29/07 - meeting has been postponed, but Serena is
working on a strategy to work with Telelogic.
b.. We need to put in a request to have approval to include Axis 2,
JDOM, and Open SAML 1.1 in our downloads. Tim and Brian will work this.
01/18/07 - no progress yet. 01/29/07 - no formal progress, but Brian is
going through Open SAML right now. Our issue here is to ensure that we can
build on these and refer to them. Brian says that this really effects our
products such as TT-Vail more than releasing ALF 1.0. We'll begin building
with Axis 2 for Milestone .8.
c.. Brian is concerned about his time to write up the test plans. He's
got a draft document that he'll provide to Cognizant and then work
incrementally to expand.
Decisions
a.. BPEL has acknowledged a bug with RPC literals. They offered a
workaround, but Tim doesn't want to introduce that into ALF. BPEL will have
a fix for this in 2-3 weeks. Justin will note this in a Readme.
b.. We're adding another build to .7 to pick up some bug fixes.
Actions
1. Demo - needs to be clearer - Kevin Parker
2. About ALF - page has different audiences and needs to talk to them
differently. Need to whack Eclipse junkies over the head to understand that
ALF is different. Content tailored to communities, publishers, consumers and
Eclipse-junkies - Kelly Shaw - done and waiting on Kevin to update the
Eclipse website.
3. Home page - needs updating - jazzing up - Kevin Parker
4. Downloads Page - needs updating - Tim Buss - done
5. FAQ - Brian Carroll - 01/29/07 - Still in progress
6. ALF in the news - Kevin Parker
7. Requirements - duplicate what's on the team page - Kevin Parker
8. NAV BAR - Fix It Kevin - Communities - Kevin Parker
9. Vocabularies - add narrative - Kelly Shaw - 01/11/07 - no progress
expected until after SKO.
10. Schedules/Milestones - Tim Buss/Kim Beckham done
11. Need to breakout the post 1.0 tasks into a secondary schedule that we
can cleanup and post to Eclipse site. Brian Carroll/Kim Beckham done
12. Communities (not Ecosystem) - developers/extenders/users - Kevin - get
list update