[news.eclipse.technology.alf] ALF Weekly Project Meeting 01/18/07
|
Meeting Reminder:
Dial-in Numbers
US: 1-800-547-4000 (Conf ID 878853)
UK: 08082380604 (Conf ID 878853)
WebEx
Topic: ALF Weekly Project Meeting
Date: Every 1 week on Thursday, from Thursday, December 7, 2006 to Thursday,
March 1, 2007
Time: 12:00 pm, Mountain Standard Time (GMT -07:00, Denver) Meeting number:
571 356 852 Meeting password: alf10
Please click the following link to view or edit your meeting information, or
to start your meeting.
<https://serena.webex.com/serena/j.php?ED=92369792>
Notes from 01/11/07 Meeting
Eclipse Review Process
a.. Brian will be scheduling the review for Milestone .7 for February,
depending on the final analysis by Kim and Summer on the impact of having
the three Cognizant developers taking the week of Christmas off. 01/11/07 -
Brian says this will be a release review. Next week we should be able to
decide when we want to schedule this. Brian will send out some draft slides
and a reminder of the criteria required for this review.
b.. QA will be posting test plans and test results to the Eclipse site
based on turnover 03-Feature Complete. 01/04/07 - QA has files that can be
posted. Robert will make these PDF format and send to Tim, Brian, Mary, and
Kim for review. 01/11/07 - We haven't had a chance to review this PDF yet.
Robert would like to establish a way to post this info. Robert will look
into using the WIKI with his Bugzilla ID. If this doesn't work, he'll talk
to Brian about posting the PDF to the site.
Project Schedule
a.. Project schedule reviewed and updated in today's meeting. Latest
versions will be posted to Serena internal Sharepoint site and to the
Eclipse website as well.
Other:
a.. 12/07/06 Brian met with Telelogic this morning to discuss possible
in ALF integrations. No bandwidth, not really interested. Presented
ALF/Applications to the Serena reps to the partners earlier in the week.
Direct presentation to the partners is desirable; Brian will work on setting
that up. 01/11/07 - Some additional meetings are happening. We'd like to
get Telelogic involved in the requirements Vocabulary. Brian has contacted
Keven Parker and Kelly Shaw about this.
b.. There's a new open source project starting and Creation Review is
scheduled for next Wednesday. This is a workflow/designer project.
c.. We need to put in a request to have approval to include Axis 2,
JDOM, and Open SAML 1.1 in our downloads. Tim and Brian will work this.
01/11/07 - no progress yet.
Decisions
a.. We'll step back and use a standard ZIP file for delivery rather than
using a self-extracting ZIP file. We'll start this with turnover 04.
b.. Milestone .7 will not be converted to Release 1.0.
Actions
1. Demo - needs to be clearer - KevinParker
2. About ALF - page has different audiences and needs to talk to them
differently. Need to whack Eclipse junkies over the head to understand that
ALF is different. Content tailored to communities, publishers, consumers and
Eclipse-junkies - Kelly Shaw - done and waiting on Kevin to update the
Eclipse website.
3. Home page - needs updating - jazzing up - KevinParker
4. Downloads Page - needs updating - Tim Buss - 01/11/07 - TBD
5. FAQ - Brian Carroll - 01/11/07 - In progress
6. ALF in the news - Kevin Parker
7. ALF Team - needs some edits phone/webex - Tim Buss - done
8. Requirements - duplicate what's on the team page - Kevin Parker
9. NAV BAR - Fix It Kevin - Communities - Kevin Parker
10. Vocabularies - add narrative - Kelly Shaw - 01/11/07 - no progress
expected until after SKO.
11. Schedules/Milestones - Tim Buss/Kim Beckham
12. Need to breakout the post 1.0 tasks into a secondary schedule that we
can cleanup and post to Eclipse site. Brian Carroll/Kim Beckham
13. Communities (not Ecosystem) - developers/extenders/users - Kevin - get
list update