[wtp-pmc] end game proposal

A strawman proposal for the WTP end game; we can discuss during the call.

 

Post M5:

  • All API changes require project lead approval
  • All changes require associated Bugzilla entry
  • PMC will review defect convergence on a weekly basis (daily as needed during final RC candidate production)

 

Week of July 3:

  • RC1 produced
  • Any defect can be addressed
  • Component lead must code review and approve all fixes (enter into Bugzilla record and checkin notes)

 

Week of July 10:

  • RC2 produced
  • P1/2 only can be addressed
  • All checkins must have Bugzilla entry
  • Component lead must code review and approve

 

Week of July 17:

  • RC3 produced
  • P1 only can be addressed
  • Project lead (or designate) must approve; component lead must code review (enter both names into Bugzilla record and checkin notes)

 

Week of July 24:

  • RC’s produced as needed
  • P1 only can be addressed
  • PMC approval required for checkin, plus two component leads must code review (enter all three names into Bugzilla record and checkin notes)
  • Each RC requires testing on all platforms

 

Final review:

  • No P1’s admitted (i.e., no ship-killer defects known)
  • All automated tests passing on final RC
  • All shipping platforms have been tested
  • All component leads sign off on individual components
  • PMC votes to release

 