The WTP PMC approved the following 1.5.1 rampdown plan
today; note that this includes dates where we coordinate with other Callisto
projects since this is a joint release.
WTP will be providing a maintenance release in line with
other Callisto projects (see Callisto Coordinated Maintenance).
August 15: Final date
for any hot bug requests to be submitted
against WTP 1.5.1; subsequent
requests will apply to the 1.5.2 maintenance line.
August 30: RC3 (final?) for platform 3.2.1 [See the platform’s endgame plan for more
details]
September 01: Component lead triage begins. All bugs reviewed and
targeted accordingly; most P3 and low sev bugs not yet addressed that are
nontrivial should be pushed out of the 1.5.1 release.
September 08: WTP 1.5.1 code complete. Start of PMC-level triage.
September 15: Code freeze for WTP 1.5.1 and start of downstream
projects’ (TPTP, e.g.) final readiness and verification cycle. (Any
requested changes or P1 bugs discovered required PMC approval to fix.)
September 15: Date by which all Callisto projects are maintenance
build ready and update site loading/testing can commence.
September 27: Final posting of Callisto bits and mirror
synchronization; update site locked during this time.
September 29: GA for first Callisto maintenance pack (including
base 3.2.1 and WTP 1.5.1). Callisto update site, WTP update site, and WTP
download page all available.(including all-in-one bundles for WTP 1.5.1).