[wtp-dev] Minutes of the WTP Status Telecon, 2006-06-01
|
See WTP Status Telecons [1] for more
information.
[1] http://eclipse.org/webtools/development/status-telecons/index.html
Attendees
Amy Wu
Arthur Ryman
Chris Brealey
Chuck Bridgham
Craig Salter
David Williams
Der Ping Chou
Jeffrey Liu
John Lanuti
Kate Price
Kathy Chan
Keith Chong
Konstantin Komissarchik
Larry Dunnell
Larry Issac
Lawrence Mandel
Nitin Dahyabhai
Raghu Srinivasan
Ted Bashor
Tim Deboer
Thomas Yip
Tim Wagner
1. WTP 1.5 Status
WTP 1.5 milestones plan [1]
Milestone
|
Date
| Description
|
RC4
|
Wednesday, 31-May-06
| Component lead approval and wtp-dev notification
required for all checkins
|
WTP Freeze
|
Wednesday, 14-June-06
| WTP "cooldown" begins; only PMC-approved
(ship-stopping) issues addressed hereafter
|
RC5
|
Tuesday, 20-Jun-06
| WTP release candidate; platform-level triage
(PMC approves changes with downstream consumer sign off)
|
RC6
|
Wednesday, 28-Jun-06
| Gold master
|
GA
|
Friday, 30-Jun-06
| Callisto GA (WTP 1.5 GA Release, English
only) |
[1] http://www.eclipse.org/projects/callisto.php
Important: From now on, use the target milestone
field to indicate what you intend to fix in the 1.5 release. Bugs that
we intend to fix in 1.5 should be targeted to 1.5 RC5. Others should be
deferred. We don't want anything targeted to RC6 unless it is truely truely
stop ship and we cannot fix it in RC5. Bugs targeted to RC5 should have
a P1 or P2 priority.
Arthur - Let's go around the table to see what we are
intending to fix for each component.
Tim - Have a few open bugs that look ugly. Will investigate
and may ask for approval for this release, but they are not stop ships.
Chris - Have 19 open bugs. Target to fix them by the next
couple weeks.
Craig - Have 8 bugs that we want to fix. Comfortable fixing
them before code freeze
Chuck - We have 28 targetted to 1.5. 7 or 8 have requested
for PMC approval. 9 of them are P3. The rest we feel comfortable getting
them in before code freeze.
David - Have 5 or 6 for RC5 and others that will investigate
and can be defered.
Der Ping - Will target bugs according to the process.
No estimate on how many bugs RDB wants to fix at this moment.
1.1 WTP 1.5 Build Status
- David Williams
David - RC4 is declared, it's available on the update site.
For next week, 1.0.3, code in by Monday, smoke test by Tuesday and declare
on Wednesday. For 1.5, code in by Wednesday, smoke test on Thursday and
declare on Friday.
David - Please complete updating plug-in version numbers
by this week.
David - There's a tool available to help you update version
numbers, but it only works if the current plug-in version is accurate.
Will investigate the tool.
Kathy - Will you handle the feature version numbers?
David - Yes, they are completed.
1.2 Bugs Waiting for
PMC Approval [1] - Jeffrey Liu
[1] http://www.eclipse.org/webtools/plans/1.5/ramp-down-bugs-approval.html
Arthur - All bugs need to have a patch, well tested and
safe.
Arthur - When you accept patches from contributors, make
sure you update the IP log.
Tim W - Send me an email if you need more information on
how to update the IP log.
Arthur - There will be meetings at 3:00 pm EST each day
for PMC members to approve bugs. You can bring both 1.5 and 1.0.3 bugs
to the meeting. Attendant is optional. This will start next Monday.
1.3 WTP 1.5 Hot Bugs
[1] - Jeffrey Liu
[1] https://bugs.eclipse.org/bugs/buglist.cgi?short_desc_type=allwordssubstr&short_desc=%5Bhotbug%5D&classification=WebTools&product=Web%20Tools&target_milestone=1.5%20M4&target_milestone=1.5%20M5&target_milestone=1.5%20M6&target_milestone=1.5%20RC1&target_milestone=1.5%20RC2&target_milestone=1.5%20RC3&target_milestone=1.5%20RC4&target_milestone=1.5%20RC5&target_milestone=1.5%20RC6&target_milestone=1.5.1%20M151&bug_status=UNCONFIRMED&bug_status=NEW&bug_status=ASSIGNED&bug_status=REOPENED
1.4 WTP 1.5 Hot Bug
Requests [1] - Jeffrey Liu
Owners should update the bug status prior
to the status telecon.
[1] https://bugs.eclipse.org/bugs/buglist.cgi?short_desc_type=allwordssubstr&short_desc=%5Bhotbug_request%5D&classification=WebTools&product=Web%20Tools&bug_status=UNCONFIRMED&bug_status=NEW&bug_status=ASSIGNED&bug_status=REOPENED
1.5 P1 Bugs [1] - Jeffrey
Liu
https://bugs.eclipse.org/bugs/buglist.cgi?classification=WebTools&product=Web+Tools&bug_status=UNCONFIRMED&bug_status=NEW&bug_status=ASSIGNED&bug_status=REOPENED&priority=P1
1.6 P2 Bugs [2] - Jeffrey
Liu
https://bugs.eclipse.org/bugs/report.cgi?x_axis_field=target_milestone&y_axis_field=assigned_to&z_axis_field=&query_format=report-table&classification=WebTools&product=Web+Tools&bug_status=UNCONFIRMED&bug_status=NEW&bug_status=ASSIGNED&bug_status=REOPENED&priority=P2&format=table&action="">
1.7 Blocking Bugs [1]
- Jeffrey Liu
https://bugs.eclipse.org/bugs/buglist.cgi?classification=WebTools&product=Web+Tools&bug_status=UNCONFIRMED&bug_status=NEW&bug_status=ASSIGNED&bug_status=REOPENED&bug_severity=blocker
1.8 Critical and Major
Bugs [1] - Jeffrey Liu
https://bugs.eclipse.org/bugs/report.cgi?x_axis_field=target_milestone&y_axis_field=assigned_to&z_axis_field=&query_format=report-table&classification=WebTools&product=Web+Tools&bug_status=UNCONFIRMED&bug_status=NEW&bug_status=ASSIGNED&bug_status=REOPENED&bug_severity=critical&bug_severity=major&format=table&action="">
1.9 Bugs to be Triaged
[1] - Jeffrey Liu
QA owners should triage these bugs.
[1] https://bugs.eclipse.org/bugs/report.cgi?x_axis_field=bug_severity&y_axis_field=qa_contact&z_axis_field=&query_format=report-table&classification=WebTools&product=Web+Tools&bug_status=UNCONFIRMED&bug_status=NEW&bug_status=ASSIGNED&bug_status=REOPENED&emailassigned_to1=1&emailtype1=substring&email1=inbox&format=table&action="">
1.10 Bugs Targeted to
Past Milestones/Release Candidates [1] - Jeffrey Liu
There are currently bugs targeted to 1.5 M4, 1.5 M5, 1.5 M6, 1.5 RC1, 1.5
RC2, 1.5 RC3 and 1.5 RC4. These milestones and release candidates have
already been declared. Bug owners should retarget these bugs.
[1] https://bugs.eclipse.org/bugs/report.cgi?x_axis_field=target_milestone&y_axis_field=assigned_to&z_axis_field=&query_format=report-table&classification=WebTools&product=Web+Tools&target_milestone=1.5+M4&target_milestone=1.5+M5&target_milestone=1.5+M6&target_milestone=1.5+RC1&target_milestone=1.5+RC2&target_milestone=1.5+RC3&target_milestone=1.5+RC4&bug_status=UNCONFIRMED&bug_status=NEW&bug_status=ASSIGNED&bug_status=REOPENED&format=table&action=""
1.11 Process to Submit Bugs for PMC Approval - Jeffrey Liu
The new process to sumbit a bug for PMC approval is to
add the word PMC to the bug's status whiteboard.
1.12 Versioning of Plug-ins
Reused in Other Projects - Jeffrey Liu
TPTP is re-using our Xerces featues and plugins, just like
we are re-using the org.eclipse.equinox.servlet.api plug-in from the Equinox
component. When WTP and TPTP each builds these features and plugins, they
have different 4th digit qualifiers. When an adopter pulls in both WTP
and TPTP, there are two copies of the same content floating around. Although
there's no known functional problems reported, adopters have expressed
concern about this. One suggestion proposed is to hard-code the 4th digit.
Any other suggestions/concerns/comments?
2 WTP 1.0.3 Status -
David Williams
2.2 WTP 1.0.3
approved bugs [1]
- Jeffrey Liu
[1] http://www.eclipse.org/webtools/plans/1.0.3/ramp-down-bugs-approval.html
3. Other Business -
Open
Test coverage for all WTP classes/methods[1]
[1] http://download.eclipse.org/webtools/downloads/drops/S-1.5RC3-200605182217/apiresults/full_test_coverage/api-tc-summary.html
Thanks,
Jeffrey Liu
IBM Rational Software
IBM Toronto Lab.
8200 Warden Ave. Markham, Ontario, L6G 1C7
Internal mail: D3/UMZ/8200/MKM (D3-268)
T/L: 969 3531
Tel: (905) 413 3531
Fax: (905) 413 4920
jeffliu@xxxxxxxxxx