Re: [wtp-dev] M5 Declaration Plan - re-spining the re-spin


I have tested this driver and declare it a success!

We have some work to do in M6 - but from J2EE team standpoint, M5 is a GO

Thanks - Chuck

Rational J2EE Tooling Team Lead
IBM Software Lab - Research Triangle Park, NC
Email:  cbridgha@xxxxxxxxxx
Phone: 919-254-1848 (T/L: 444)



David M Williams/Raleigh/IBM@IBMUS
Sent by: wtp-dev-bounces@xxxxxxxxxxx

06/30/2005 04:04 PM

Please respond to
"General discussion of project-wide or architectural issues."

To
"General discussion of project-wide or architectural issues." <wtp-dev@xxxxxxxxxxx>
cc
Subject
Re: [wtp-dev] M5 Declaration Plan - re-spining the re-spin






And ... as luck would have Chuck confirmed right away that the 'respin' did not contain the fix he was attempting to get in, as previously posted: blocking defect 102171 (
Issues with EAR import)
https://bugs.eclipse.org/bugs/show_bug.cgi?id=102171 (and others).


As best we can tell, everything was tagged and released correctly (using extssh) but when the build machine went to build it (using pserver) ... 15-20 minutes later ... the extssh/pserver replication had not occurred, so it built the "old" stuff.

I've started a respin, and "manually" double checked the map files the build machine pulled down and confirmed they contain the correct version numbers Chuck was expecting ... so next one should be golden. New ETA for this final final build is 6 PM

Sorry for the chuuurrrrn,





Arthur Ryman <ryman@xxxxxxxxxx>
Sent by: wtp-dev-bounces@xxxxxxxxxxx

06/30/2005 03:45 PM

Please respond to
"General discussion of project-wide or architectural issues."

To
wtp-dev@xxxxxxxxxxx
cc
Subject
[wtp-dev] M5 Declaration Plan








At the status telecon today we agreed to do final testing on the latest I-build and report test results by 5pm EDT. Only J2EE has approval to release any more fixes if the current I-Build fails verfication.


If the current I-Build passes manual testing, it will be declared as M5.


Arthur Ryman,
Rational Desktop Tools Development

phone: +1-905-413-3077, TL 969-3077
assistant: +1-905-413-2411, TL 969-2411
fax: +1-905-413-4920, TL 969-4920
mobile: +1-416-939-5063, text: 4169395063@xxxxxxx
intranet: http://labweb.torolab.ibm.com/DRY6/
_______________________________________________
wtp-dev mailing list
wtp-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/wtp-dev

_______________________________________________
wtp-dev mailing list
wtp-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/wtp-dev


Back to the top