Skip to main content

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index] [List Home]
Re: [sequoyah-dev] [GSoC] Weekly status report template

Hi,

Accomplished last week
These last two weeks I worked on fixing bugs that were reported by my tutors, they helped me a lot giving me fast feedback for each patch sent.
The main bug fixed was do the editor handle with an i18n folder located anywhere in the project.

Planned for this week
This week I want do that the editor handle with a folder with any name and continue working with my tutors testing and finding other bugs.

2011/7/26 Lucas Tiago Castro Jesus <lucastdcj@xxxxxxxxx>
Hi,

Accomplished last week
How I had planned I did some corrections in the string handling, now it's able to handle with multi-line strings.
Furthermore, I uploaded the first version of the project [1] which can do correctly the basic things like add, remove, insert and change a string and a file.

Planned for this week
This week I want to continue testing the editor to find eventually bugs, as well as improve the documentation of the code.

[1] https://bugs.eclipse.org/bugs/show_bug.cgi?id=353164


Thank you for your attention
Heve a nice week
 
Lucas DE CASTRO

2011/7/19 Lucas Tiago Castro Jesus <lucastdcj@xxxxxxxxx>
Hi,

Accomplished last week
This week, I improved the code in some aspects like:
- The editor handle with all messages properties file in a package, that is with files of the type  "messages_en.properties" and "messages_en_US.properties".
- I cleaned the code, removing some debug and comment lines.
- Also, I done some tests with string with special characters

Planned for this week
For this week, I want that the code handle with all types of string, in my tests, I saw that for string with, for example, "\n\" the code doesn't work correctly. Furthermore, I will improve the documentation of the code.


Thank you for your attention
Heve a nice week
 
Lucas DE CASTRO


2011/7/11 Lucas Tiago Castro Jesus <lucastdcj@xxxxxxxxx>
Hi,
 
Accomplished last week
This week I finished importants functionalities of the project ,i.e, we are able to add/remove/update a string and also add/update/remove a localization file.
 
Planned for this week
For this week, I want to improve the code in some aspects like:
- The editor must be able to handle with all messages properties file in a package, now we handle just with the properties files in the "i18n" folder
- I will test the plugin for some specials values for one string, for example, string with special characters. Eventually do some specials cases
 
Furthermore I want to start the documentation and "clean" the code, i.e., remove some lines of debugs and tests
Finally, I have tomorrow my weekly meeting with my mentors.
 
Thank you for your attention
Heve a nice week
 
Lucas DE CASTRO

 



 
2011/7/5 Lucas Tiago Castro Jesus <lucastdcj@xxxxxxxxx>
Hi,

You can find this week's activities at: http://lucastdcj.wordpress.com/2011/07/04/3006-0507/


Have a nice week,
Lucas De Castro

2011/6/28 Lucas Tiago Castro Jesus <lucastdcj@xxxxxxxxx>
This week I took an important step, more specifically, the project can open correctly a property file and recognize correctly the nature of the project

Also I discussed with my tutors a possible structure for dealing with the properties files - load the keys and values.

Tomorrow I will have my weekly meeting with Daniel and Marcel to discuss  the source code and propose new milestones.

A small problem I had this week was to debug the code, because eclipse stopped when I tried it. So I started to debug manually.


2011/6/21 Lucas Tiago Castro Jesus <lucastdcj@xxxxxxxxx>
This week I would like that the project were able to read and modify properties files.

In order to do that I continued what I had begun in lasts weeks - work in the package org.eclipse.sequoyah.localization.pde. Friday I sent a bug fix 349735 showing the begin of this work.

During the weekend I kept changing the methods implemented in this package and did some tests on the Android version to better understand some of the considerations made. Furthermore I started a documentation of this package, explaining the methods and giving some examples.

Tomorrow I will correct some errors in org.eclipse.sequoyah.localization.pde.manager and make the weekly meeting with my tutors to they help me in some issues and set the milestones of this week.


2011/6/14 Lucas Tiago Castro Jesus <lucastdcj@xxxxxxxxx>
Accomplished last two weeks:
  • These last two weeks I worked on the new schema that will make the editor understand Eclipse projects, in order to do that I worked on the package "org.eclipse.sequoyah.localization.pde"
  • Also I finished the french translation of some components [1]
Planned for this week
  •  I will have a meeting tomorrow with my tutors, who will help me with some issues and also help to fix the milestones for the next weeks.
Last weeks I've been a little busy with the last tests and work at my university, but now I can devote myself completely to the project.

[1]: https://bugs.eclipse.org/bugs/show_bug.cgi?id=347637


2011/5/30 Lucas Tiago Castro Jesus <lucastdcj@xxxxxxxxx>
Hi all,


As usual, here is the report of my activities this week:

Planned for last week:
  • For last week I would like to start the developement of "org.eclipse.sequoyah.localization.pde" package that will allow to localize, for instance, properties files.
Accomplished last week:
  • This week I corrected some problems existing in the french translation and I sent it in a patch
  • I started to work on the "org.eclipse.sequoyah.localization.pde" defining the constants in "IPDELocalizationSchemaConstants.java" file and also I studied the codes "AndroidLocaleAttribute.java" and "AndroidLocalizationSchema.java"
Planned for this week
  • This week I would like to modify the files PDELocaleAttribute.java and PDELocalizationSchema.java

Thank you.
Lucas De Castro


2011/5/16 Lucas Tiago Castro Jesus <lucastdcj@xxxxxxxxx>
Hello,

Here is the report of my activities this week:

Planned for last week:
  • Get more familiar with the code Sequoyah
  • Do my first patch
  • And make tests by myself with the code.
Accomplished last week:
  • To get more familiar with the Sequoyah code and make tests with the code by myself, I developed android applications, so I could better understand the functioning of the LFE.
  • To my first patch, I started doing the French version of the project, it will let me to better understand each component of the code.
Planned for this week
  • For this week I would like to finish this patch
Risks and Main Obstacles:
  • Still the same, that is, university tests and work until the first week of June.
If you have some questions or suggestions, please do not hesitate.

Have a nice week,
Lucas De Castro


2011/5/23 Lucas Tiago Castro Jesus <lucastdcj@xxxxxxxxx>
Hello,

As usual, here is
the report of my activities this week:

Planned for last week:
  • For this week I would like to finish my first patch
Accomplished last week:
  • This week, I finished the French version of the project, this includes translate properties files, so I did manually what our final project must do.
  • I also discussed with my tutors on the project development.
Planned for this week
  • For this week I will start the developement of "org.eclipse.sequoyah.localization.pde" package that will allow to localize, for instance, properties files.
Risks and Main Obstacles:
  • Still the same, that is, university tests and work until the first week of June.

Thank you.
Lucas De Castro


2011/5/16 Lucas Tiago Castro Jesus <lucastdcj@xxxxxxxxx>
Hello,

Here is the report of my activities this week:

Planned for last week:
  • Get more familiar with the code Sequoyah
  • Do my first patch
  • And make tests by myself with the code.
Accomplished last week:
  • To get more familiar with the Sequoyah code and make tests with the code by myself, I developed android applications, so I could better understand the functioning of the LFE.
  • To my first patch, I started doing the French version of the project, it will let me to better understand each component of the code.
Planned for this week
  • For this week I would like to finish this patch
Risks and Main Obstacles:
  • Still the same, that is, university tests and work until the first week of June.
If you have some questions or suggestions, please do not hesitate.

Have a nice week,
Lucas De Castro



2011/5/9 Lucas Tiago Castro Jesus <lucastdcj@xxxxxxxxx>

Hi,


First of all, thank you very much for this opportunity, I am so glad to work with you so I will do my best and work hard on this project.  


- Planned for last week


    For last week I had planned to get familiar with the Eclipse environment and install  development environment.


- Accomplished last week

    In order to get familiar with the Eclipse environment ,  I done the tutorials:


    In order to install the development environment Marcel Gorri and Daniel Pastore helped me to have exactly the same environment used by Sequoyah developers.


- Planned for this week

    For next week, I want:

    • Get more familiar with the Sequoyah code
    • Do my first patch
    • And make tests by myself with the code.

- Risks

    One risk that will be present until first week of June, is the university works. This month I have a lot of works and tests, but I will do my best. I plan to work 15h


- Main obstacles

    For this adaptation phase, I think I will not have an other obstacle different of the university tests.


Again, thank you very much!


Regards,

Lucas De Castro



2011/5/9 Marcel Gorri <wmg040@xxxxxxxxxxxx>
Hi Lucas, 

as it was suggested to other projects, it would be useful if we could have some sort of mechanism to follow up the status of your activities. It is good for both sides in terms of planning and organization. This way, our suggestion is that you send us every week to this mailing list, a short status report containing the following info:

- Planned for this week

- Accomplished this week

- Planned for next week

- Risks

- Main obstacles


You could send this report every monday, for instance, and if you join our open meeting, we could discuss any point you believe it is necessary in this meeting. (of course, we can have other meetings, if necessary)


If you have any comments or suggestions, please let us know.


Best,

 Marcel


_______________________________________________
sequoyah-dev mailing list
sequoyah-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/sequoyah-dev




--
==================================
Lucas Tiago de Castro Jesus
http://www.algoritmo.110mb.com
Engenharia de Computação (EC08) - Unicamp
==================================



--
==================================
Lucas Tiago de Castro Jesus
http://www.algoritmo.110mb.com
Engenharia de Computação (EC08) - Unicamp
==================================



--
==================================
Lucas Tiago de Castro Jesus
http://www.algoritmo.110mb.com
Engenharia de Computação (EC08) - Unicamp
==================================



--
==================================
Lucas Tiago de Castro Jesus
http://www.algoritmo.110mb.com
Engenharia de Computação (EC08) - Unicamp
==================================



--
==================================
Lucas Tiago de Castro Jesus
http://www.algoritmo.110mb.com
Engenharia de Computação (EC08) - Unicamp
==================================



--
==================================
Lucas Tiago de Castro Jesus
http://www.algoritmo.110mb.com
Engenharia de Computação (EC08) - Unicamp
==================================



--
==================================
Lucas Tiago de Castro Jesus
http://www.algoritmo.110mb.com
Engenharia de Computação (EC08) - Unicamp
==================================



--
==================================
Lucas Tiago de Castro Jesus
http://www.algoritmo.110mb.com
Engenharia de Computação (EC08) - Unicamp
==================================



--
==================================
Lucas Tiago de Castro Jesus
http://www.algoritmo.110mb.com
Engenharia de Computação (EC08) - Unicamp
==================================



--
==================================
Lucas Tiago de Castro Jesus
http://www.algoritmo.110mb.com
Engenharia de Computação (EC08) - Unicamp
==================================



--
==================================
Lucas Tiago de Castro Jesus
http://www.algoritmo.110mb.com
Engenharia de Computação (EC08) - Unicamp
==================================



--
==================================
Lucas Tiago de Castro Jesus
http://www.algoritmo.110mb.com
Engenharia de Computação (EC08) - Unicamp
==================================