Re: [platform-releng-dev] Eclipse Oxygen M1 reminders

Master is open again. You can go ahead and submit for Oxygen


Thanks and Regards,
Sravan

Sravan Kumar Lakkimsetti
IBM India Pvt Ltd,
Embassy Golf Links Business Park, D Block,
Off Indiranagar-Kormangla Inner Ring Road,
Bangalore - 560071, India
Phone: 91-80-41776858

Inactive hide details for "Andrey Loskutov" ---08-08-2016 05:15:55 PM---Hi,   May be I've missed the mail, but since Oxigen M1 "Andrey Loskutov" ---08-08-2016 05:15:55 PM---Hi, May be I've missed the mail, but since Oxigen M1 is delivered now, is the master opened again

From: "Andrey Loskutov" <loskutov@xxxxxx>
To: platform-releng-dev@xxxxxxxxxxx
Cc: "Eclipse platform release engineering list." <platform-releng-dev@xxxxxxxxxxx>
Date: 08-08-16 05:15 PM
Subject: Re: [platform-releng-dev] Eclipse Oxygen M1 reminders
Sent by: platform-releng-dev-bounces@xxxxxxxxxxx





Hi,

May be I've missed the mail, but since Oxigen M1 is delivered now, is the master opened again for work?

Kind regards,
Andrey Loskutov

http://google.com/+AndreyLoskutov


Gesendet: Freitag, 29. Juli 2016 um 10:28 Uhr
Von:
"Sravan K Lakkimsetti" <sravankumarl@xxxxxxxxxx>
An:
"Eclipse platform release engineering list." <platform-releng-dev@xxxxxxxxxxx>
Betreff:
[platform-releng-dev] Eclipse Oxygen M1 reminders

Hi,

Eclipse Oxygen M1 Stabilization starts next week with a goal to deliver on Aug 05, 2016.

The build schedule has been updated and can be downloaded from
https://www.eclipse.org/eclipse/platform-releng/buildSchedule.html

Please note

    • Monday we have the last day of development (and even then, no "big changes"). After Monday, no feature work or unrelated fixes are allowed -- only regression fixes.
    • Tuesday all day test pass . No one should develop or fix anything, but literally spend the entire day testing.
    • Wednesday is the fix-day with a focus on fixing regressions found during the test-day(tuesday). No unrelated fixes
    • The last Wednesday build is the release candidate every team signs-off on Thursday. Signing-off may involve some re-testing, or at least confirming no changes have been made to your components code since the last time the component was tested well.
    • No new code changes can be made until the milestone is officially declared. That is, it is not enough that your component has signed off.

Thanks and Regards,
Sravan

Sravan Kumar Lakkimsetti
IBM India Pvt Ltd,
Embassy Golf Links Business Park, D Block,
Off Indiranagar-Kormangla Inner Ring Road,
Bangalore - 560071, India
Phone: 91-80-41776858
_______________________________________________ platform-releng-dev mailing list platform-releng-dev@xxxxxxxxxxx To change your delivery options, retrieve your password, or unsubscribe from this list, visit
https://dev.eclipse.org/mailman/listinfo/platform-releng-dev_______________________________________________
platform-releng-dev mailing list
platform-releng-dev@xxxxxxxxxxx
To change your delivery options, retrieve your password, or unsubscribe from this list, visit
https://dev.eclipse.org/mailman/listinfo/platform-releng-dev



Back to the top