Bjorn,
It the group needs more time to provide
feedback then we can certainly move the date. However, we have been
collecting feedback for well over 1 month, so I feel like we should be moving
to close down the development and move on to other things. Considering you
are the process king how would you suggest we finish up the project?
Ian
From: phoenix-dev-bounces@xxxxxxxxxxx
[mailto:phoenix-dev-bounces@xxxxxxxxxxx] On
Behalf Of Bjorn Freeman-Benson
Sent: October 11, 2006 2:09 AM
To: For
developers on the new Eclipse.org website project.
Subject: Re: [phoenix-dev] Home
page RC2
I think this schedule is a little aggressive. In
development process-land, we use "one week" as the minimum time to
gather feedback from the community. Especially since many of the leaders of the
Eclipse community are at the Eclipse Summit Europe conference in Germany this
week. Thus "one day" is a bit short. FYI.
Ian Skerrett wrote:
It would be appreciated if you can provide feedback
before end of business on Wednesday.