Re: [mylyn-dev] release plan

Thanks Matthias. As discussed on today's call we'll go with the following plan:

Projects:
 Commons, Context, Docs, Tasks   /   Builds, Reviews, Versions   /   EGit

Indigo:

 Dec 2010:    -    /    -    /  0.10
 Mar 2011:  3.5  /  0.7  /  0.11
 Jun 2011:  3.6  /  0.8  /  1.0

Indigo+1 (tentative):

 Nov 2011:  3.7  /  0.9  /  1.x
 Jun 2012:  4.0  /  1.0  /  1.x

The Incubator project does not have releases by definition.

I will create 0.7 milestones for the Builds and Versions project shortly.

Steffen


On Thu, Nov 25, 2010 at 2:34 PM, Matthias Sohn
<matthias.sohn@xxxxxxxxxxxxxx> wrote:
[...]
> Current EGit/JGit release schedule is
>   Dec 15 2010 : 0.10
>   Mar 2011 : 0.11
>   June 2011 (Indigo) : 1.0
> We do this 3 monthly cycle since our first release at Eclipse in Mar 2010
> (0.7)

-- 
Steffen Pingel
Committer, http://eclipse.org/mylyn