I see there are still ~ 60 defects targeted
at 3.1. I had asked that all defects not going to be done in 3.1 be retargeted
and reviewed with me. This leave ~ 130 for 3.2.
It seems the retargeting may have been
at least partly done, but based on the plan we have 2 weeks of full testing
and prioritized debugging. It is not clear to me how this can be contained,
so I would like to discuss slipping entry of the test phase by 1 week and
the impact of that. Basically this would mean a full week starting now
to tackle the defect backlog to clear these 60+ defects thus giving us
more stability before the final testing of 3.1.