Re: [higgins-dev] Agenda for Thursday's higgins dev call

The H1.1M8 build is marked RESOLVED, and has been for a while. I am not sure what the process is to change it to CLOSED.

We are close to finished on H1.1M8 (last pieces are fixing a link to GTK Selector download to point at Azigo’s copy (Novell has removed it from their site) which should be done by the meeting).

H1.1M9 is delayed until 22-Oct – remaining tasks are updating autobuild wiki page and Apple Approved Higgins Branded iPhone selector.

There are some 1.1 issues that are currently not attached to a milestone that need to be cleaned up (many are relatively minor H1.1 STS issues that will become mute when Higgins 2.0 (CardPRess based) STS is submitted).

Assuming none of those issues are show stoppers, we could potentially have RC1 as M9 (22-Oct).

 

Regards,

Mike

 

From: higgins-dev-bounces@xxxxxxxxxxx [mailto:higgins-dev-bounces@xxxxxxxxxxx] On Behalf Of Paul Trevithick
Sent: Wednesday, September 01, 2010 9:30 PM
To: higgins-dev developer discussions
Subject: [higgins-dev] Agenda for Thursday's higgins dev call

 

Logistics

 

  • Time: Thursday noon Eastern (16:00 UTC) U.S.
  • Skype: +9900827047990866 
  • Dial-in: 1-201-793-9022 passcode 7990866#

 

Agenda

  • [Mary] Project Plan [1] need to update (delay) 1.1M8 and 1.1M9 and 1.1RC1
    • Let's plan out new dates
  • [Mike] Review 1.1M8 [2]
    • Bugzilla says only the build itself remains to be done [3]
  • [Paul] Review recent updates to PDM 2.0
    • Overview [5]
    • persona.owl [6]
    • event.owl [7]

 

 

--Paul

 