Thanks to Andrey who rightfully pointed out I don't know which is the current Month! Dates corrected below.

Hi all,

We are scheduled to promote and contribute 4.18 RC1 to the simrel on Friday the 27th.

Here is the schedule:

Wednesday 25 Nov -- API and feature freeze, Release Candidate build

Thursday 26 Nov -- Bug verification and Sign-off 4.17 RC1

Friday 27 Nov-- 4.17 RC1 Promotion and contribution to SimRel

Please note the following excerpt from the freeze plan:

RC1

All fixes submitted must have a project lead or PMC vote on the bug report, and the fix must be reviewed by an additional committer (any committer other than the one who made the fix). A positive review from a project lead or PMC member means implicit approval and no vote is needed on the bug report. Ongoing changes to documentation, tests or examples do not require approval.

 