As it seems we have agreement (I'm taking
silence as agreement :-)), we will have our Inception iteration assessment
and planning for Elaboration iteration 1 this Friday, May 2, from 8:00AM
to 10:00AM PDT.
We will not have our regular Wednesday
call this week.
Dear committers, former discipline owners
and current practices leads - please, consider some important objectives
for this iteration:
- triage Bugzilla: please, make sure
old issues raised in Bugzilla against OpenUP 1.0 are either closed or assigned
as new practice library work, as appropriate
- new work: please, make sure each practice
has bugs raised against it, so work can be planned
Plan for next iteration - some objectives:
- get content authors up to speed with
the method authoring guidelines
- agree on objectives and how much can be done per practice
-
e.g., agree on structuring practices according to method authoring guidelines
- make sure regular calls are happening
(per practice / set of interrelated practices)
Here's the project plan we proposed
on early April (beginning of Inception):
- http://dev.eclipse.org/viewcvs/index.cgi/org.eclipse.epf/design/content_dev_plans/EPF15ContentProjectPlan.rtf?revision=1.2&root=Technology_Project
And please refer to email sent by Jim
Ruehlin to epf-dev on 4/14, subject "Re-thinking Bugzilla Prefixes"
for a reminder on what prefixes to use when creating Bugzilla entries.