Re: [epf-dev] Links from own process diagram to tasks, work products, etc

Hi Esti,

I'm not sure I followed your question, do you means you want create customize diagram in your process? If so, please follow below steps.

1. Create a supporting material in your content package
2. Insert your own process diagram into main description of supporting material
3. Create a image map link of your process diagram
4. DnD the Task (work product or others elements) to RTE then switch to HTML tab to get the element link
5. Paste the link as image map link
6. OPen your own process, switch to WBS
7. Right click on your process, select Diagrams->User Defined Diagrams
8. Check the diagram type and click 'Select'
9. Select the supporting material you created just now and click OK

Then do a browse or publish, the user defined diagram will replace the tools generated one.

Thanks & Regards, Jiang Xuan

IBM China Software Development Lab