Skip to main content

[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index] [List Home]
Re: [epf-dev] E1 Iteration Assessment and E2 Iteration Plan


Ricardo,

let's remove that objective. Since we have decided what should be done, there is no point treating the XP inclusion work any differently than any other requested content changes.... we just need to make sure to execute on 25% of total changes in each iteration, whether it is related to XP or not....

Cheers

Per Kroll
STSM, Manager Methods: RUP / RMC
Project Lead: Eclipse Process Framework
Rational Software, IBM Corp
(M) 408-219-2963



Ricardo Balduino/Cupertino/IBM@IBMUS
Sent by: epf-dev-bounces@xxxxxxxxxxx

02/01/2007 09:06 PM

Please respond to
Eclipse Process Framework Project Developers List        <epf-dev@xxxxxxxxxxx>

To
Eclipse Process Framework Project Developers List <epf-dev@xxxxxxxxxxx>
cc
Subject
Re: [epf-dev] E1 Iteration Assessment and E2 Iteration Plan






I have one comment about the following objective planned for the current iteration:


       Incorporate XP content in OpenUP – Part 1 – Ricardo

      https://bugs.eclipse.org/bugs/show_bug.cgi?id=167902

According to discussions during the resolution of this bug, new bugs were created per content area suggesting the agreed XP content to be added.

The bug referenced above has been closed.

The expectation is that each package owner would deal with the respective bugs in their areas.


Should that be part of the iteration plan instead of the bug above?


Cheers,


Ricardo Balduino
Senior Software Engineer

IBM Rational (www.ibm.com/rational)
EPF Committer (www.eclipse.org/epf)

I'm speaking at EclipseCon 2007

Per Kroll/Cupertino/IBM@IBMUS
Sent by: epf-dev-bounces@xxxxxxxxxxx

01/31/2007 07:52 PM

Please respond to
Eclipse Process Framework Project Developers List        <epf-dev@xxxxxxxxxxx>

To
"EPF Dev " <epf-dev@xxxxxxxxxxx>
cc
Subject
[epf-dev] E1 Iteration Assessment and E2 Iteration Plan








Hi,


attached you find the outcome of today's assessment and planning meeting. Feedback is appreciated.


If you own a bug that has not been closed for M4 (E1), the please either ensure it is closed asap, or move to M5 (E2). It is increasingly obvious that we

- Are not tracking to plan. We need to discuss appropriate actions in our F2F next week.

- Need new fresh blood that can help reinvigorate OpenUP development activities and build a community also around XP content


There are also a number of positives

- XP donation completed

- Good progress in several packages, such as requirements mgmt, architecture, development, and general

- Reinvigorated discussions around test


For status, see

https://bugs.eclipse.org/bugs/report.cgi?x_axis_field=bug_status&y_axis_field=assigned_to&z_axis_field=target_milestone&query_format=report-table&short_desc_type=allwordssubstr&short_desc=&classification=Technology&product=EPF&component=Content&version=0.9&version=1.0&long_desc_type=allwordssubstr&long_desc=&bug_file_loc_type=allwordssubstr&bug_file_loc=&status_whiteboard_type=allwordssubstr&status_whiteboard=&keywords_type=allwords&keywords=&bug_status=UNCONFIRMED&bug_status=NEW&bug_status=ASSIGNED&bug_status=REOPENED&bug_status=RESOLVED&bug_status=VERIFIED&bug_status=CLOSED&emailtype1=substring&email1=&emailtype2=substring&email2=&bugidtype=include&bug_id=&votes=&chfieldfrom=2006-11-01&chfieldto=Now&chfieldvalue=&format=table&action=""

Cheers

Per Kroll
STSM, Manager Methods: RUP / RMC
Project Lead: Eclipse Process Framework
Rational Software, IBM Corp
(M) 408-219-2963[attachment "E2 - Iteration Plan - EPF 2 0 Content.doc" deleted by Ricardo Balduino/Cupertino/IBM] [attachment "E1 - Iteration Assessment.doc" deleted by Ricardo Balduino/Cupertino/IBM]
_______________________________________________
epf-dev mailing list
epf-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/epf-dev

_______________________________________________
epf-dev mailing list
epf-dev@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/epf-dev


Back to the top