Re: [epf-dev] Meeting Results: I2 Iteration Assessment + I3 Iteration Planning

I can commit to the items assigned to me.

My only concern is having a delivery date of Jan 2.  Seems a bit too close
to the holidays.  Also, we're pretty much going to lose at least a week of
this iteration due to the holidays.  Can we push it back a week?

- Scott
On Thu, November 30, 2006 2:40 pm, Per Kroll said:
> Hi,
>
> attached you find the results of today's meeting.
> Filled in iteration assessment (template from OpenUP)
> Template for I3 (template from OpenUP)
>
> Please review and comment. Is the I3 Iteration plan realistic? If you have
> your name on an objective, are you committing to getting the job done in
> I3?
> I will update the project plan once we have established what the I3
> iteration plan will look like.
> Note that we
> Decided that project status is yellow, and that we should not exit
> Inception. So, E1 is now called I3.
> descoped the following from I3
> Refactor OpenUP to address scalability ? Part 1 => We first need to have
> proposals for refactoring
> Ask for feedback from EPF Composer team on OpenUP => Iteration too short,
> let's postpone that one iteration.
> We also kept a lot of the objectives from I2, and made them more specific.
>
> For those on the meeting, I made updates based on e-mail I received from
> Ana which I read first after our meeting.
>
>
> Cheers
>
> Per Kroll
> STSM, Manager Methods: RUP / RMC
> Project Lead: Eclipse Process Framework
> Rational Software, IBM Corp
> (M) 408-219-2963
>
>
>
> Per Kroll/Cupertino/IBM@IBMUS
> Sent by: epf-dev-bounces@xxxxxxxxxxx
> 11/29/2006 02:54 PM
> Please respond to
> Eclipse Process Framework Project Developers List <epf-dev@xxxxxxxxxxx>
>
>
> To
> epf-dev@xxxxxxxxxxx
> cc
>
> Subject
> [epf-dev] I2 Iteration Assessment + I3 Iteration Planning: Thu Nov 30,
> 8-10 AM PST
>
>
>
>
>
>
>
> Hi,
>
> this meeting was in the iteration plan, but I did not send out a
> reminder... Note that we by default have Iteration Assessment the last day
> of every month (since that is our iteration end)
>
> Time: Thu Nov 30, 8-10 AM PST
> Agenda:
> Walk through iteration objectives and see what objectives we addressed
> Assess whether we can exit Inception? Replan project as necessary.
> Iteration retrospective - what can we do better, we did we do well?
> Agree on iteration objectives for I3
> Produce a detailed iteration plan for I3
> Define evaluation criteria
>
> You find current plans on
> http://dev.eclipse.org/viewcvs/index.cgi/org.eclipse.epf/design/content_dev_plans/?cvsroot=Technology_Project
>
>
> Link to yahoomeeting calendar:
> http://tech.groups.yahoo.com/group/eclipseprocessframework/cal///group/eclipseprocessframework?v=4&t=1164873600&i=609&pv=2
>
>
>
>
>
>
>
> Toll-free dial-in: 1-877-421-0003
> Toll dial-in: 1-770-615-1374
> <For IBMers> Tie-line dial-in: 421-0003
> Participant passcode: 667201
>
>
>
>
>
>
> Cheers
>
> Per Kroll
> STSM, Manager Methods: RUP / RMC
> Project Lead: Eclipse Process Framework
> Rational Software, IBM Corp
> (M) 408-219-2963_______________________________________________
> epf-dev mailing list
> epf-dev@xxxxxxxxxxx
> https://dev.eclipse.org/mailman/listinfo/epf-dev
>
> _______________________________________________
> epf-dev mailing list
> epf-dev@xxxxxxxxxxx
> https://dev.eclipse.org/mailman/listinfo/epf-dev
>


Practice Leader Agile Development, IBM Rational
http://www-306.ibm.com/software/rational/bios/ambler.html

Refactoring Databases (
http://www.ambysoft.com/books/refactoringDatabases.html ) is now
available.



Back to the top