[eclipse.org-planning-council] Proposed Milestone schedule for Luna

As we discussed at today's (8/7) meeting, I have adjusted the schedule so that M6 completes before EclipseCon, even though effectively that makes M5 shorter than usual, given that many projects "lose a week" for end-of-year holidays (we often allow 7 weeks for it).

I know it "looks funny" to allocate 8 weeks for M7 ... but ... I could not really think of anything else that would really be constructive,
given the other dates we have to work with ... "end of year holidays" and "EclipseCon" week. I mean, we could have 5 RC's instead of 4, but not sure that's going to really change anything. Maybe a long M7 will give projects time to do more work on performance!

I've tried to include the schedule in this note, but not sure how well it will format, so if does not format well, please see

http://wiki.eclipse.org/Luna/Simultaneous_Release_Plan#Schedule

I'll share this on "cross-project list" as the proposed schedule, but as promised, will give you all time to discuss with your projects/adopters to see if some small tweak would be better. We will make final decision at September meeting (but, no need to wait till then ... you can post suggestions/corrections to this mailing list). But, until then ... for the first, and second, milestone, will consider it accurate so we can plan aggregation builds.
= = = = = = =

                                                              Elapsed Weeks  
      End Date                      Span from +0         for RC0   for EPP avail
M1  Friday, August 23, 2013           08/09 to 08/23          6         8   (from previous release GA)
M2  Friday, October 04                09/20 to 10/04          6         6   (from M1)
M3  Friday, November 15               11/01 to 11/15          6         6   (from M2)
M4  Friday, December 20               12/13 to 12/20          6         5   (from M3) (shift from 2 week window to 1 week window)
M5  Friday, January 31, 2014          01/24 to 01/31          6         6   (from M4) (plan to "lose" a week for end-of-year  holidays)
M6  Friday, March 14                  03/07 to 03/14          6         6   (from M5)

EclipseCon! (03/17 to 03/20)

M7  Friday, May 09                    05/02 to 05/09          8         8   (from M6) (extra week(s) for EclipseCon)
RC1 Friday, May 23                    05/16 to 05/23          2         2   (from M7)
RC2 Friday, May 30                    05/23 to 05/30          1         1   (from RC1)
RC3 Friday, June 06                   05/30 to 06/06          1         1   (from RC2)
RC4 Friday, June 13                   06/06 to 06/13          1         1   (from RC3)

Quiet week, June 16 to June 20
(no builds during "quiet week", assumed all code is done by end of RC4                        

Release Wednesday, June 25, 2014

= = = = = = =