[eclipse.org-planning-council] Proposed Milestone schedule for Luna
|
As we discussed at today's (8/7) meeting,
I have adjusted the schedule so that M6 completes before EclipseCon, even
though effectively that makes M5 shorter than usual, given that many projects
"lose a week" for end-of-year holidays (we often allow 7 weeks
for it).
I know it "looks funny" to
allocate 8 weeks for M7 ... but ... I could not really think of anything
else that would really be constructive,
given the other dates we have to work
with ... "end of year holidays" and "EclipseCon" week.
I mean, we could have 5 RC's instead of 4, but not sure that's going to
really change anything. Maybe a long M7 will give projects time to do more
work on performance!
I've tried to include the schedule in
this note, but not sure how well it will format, so if does not format
well, please see
http://wiki.eclipse.org/Luna/Simultaneous_Release_Plan#Schedule
I'll share this on "cross-project
list" as the proposed schedule, but as promised, will give you all
time to discuss with your projects/adopters to see if some small tweak
would be better. We will make final decision at September meeting (but,
no need to wait till then ... you can post suggestions/corrections to this
mailing list). But, until then ... for the first, and second, milestone,
will consider it accurate so we can plan aggregation builds.
= = = = = = =
Elapsed Weeks
End Date
Span from +0
for RC0 for EPP avail
M1 Friday, August 23, 2013 08/09
to 08/23 6
8 (from previous release GA)
M2 Friday, October 04
09/20 to 10/04 6
6 (from M1)
M3 Friday, November 15
11/01 to 11/15 6
6 (from M2)
M4 Friday, December 20
12/13 to 12/20 6
5 (from M3) (shift from 2 week window to 1 week window)
M5 Friday, January 31, 2014 01/24
to 01/31 6
6 (from M4) (plan to "lose" a week for end-of-year holidays)
M6 Friday, March 14
03/07 to 03/14 6
6 (from M5)
EclipseCon! (03/17 to 03/20)
M7 Friday, May 09
05/02 to 05/09 8
8 (from M6) (extra week(s) for EclipseCon)
RC1 Friday, May 23
05/16 to 05/23 2
2 (from M7)
RC2 Friday, May 30
05/23 to 05/30 1
1 (from RC1)
RC3 Friday, June 06
05/30 to 06/06 1
1 (from RC2)
RC4 Friday, June 13
06/06 to 06/13 1
1 (from RC3)
Quiet week, June 16 to June 20
(no builds during "quiet week", assumed all code is done by
end of RC4
Release Wednesday, June 25, 2014
= = = = = = =
Thanks,