Re: [eclipse-pmc] Updated freeze plan

I think we should mention that option to the teams (e.g. in the arch call)
but leave it up to them, given we already have mandatory test passes
scheduled.

Dani

|------------>
| From:      |
|------------>
  >--------------------------------------------------------------------------------------------------------------------------------------------------|
  |John Arthorne <John_Arthorne@xxxxxxxxxx>                                                                                                          |
  >--------------------------------------------------------------------------------------------------------------------------------------------------|
|------------>
| To:        |
|------------>
  >--------------------------------------------------------------------------------------------------------------------------------------------------|
  |eclipse-pmc@xxxxxxxxxxx                                                                                                                           |
  >--------------------------------------------------------------------------------------------------------------------------------------------------|
|------------>
| Date:      |
|------------>
  >--------------------------------------------------------------------------------------------------------------------------------------------------|
  |18.03.2010 15:07                                                                                                                                  |
  >--------------------------------------------------------------------------------------------------------------------------------------------------|
|------------>
| Subject:   |
|------------>
  >--------------------------------------------------------------------------------------------------------------------------------------------------|
  |[eclipse-pmc] Updated freeze plan                                                                                                                 |
  >--------------------------------------------------------------------------------------------------------------------------------------------------|






I have updated the draft Helios freeze plan based on the discussion at this
week's architecture call:

http://www.eclipse.org/eclipse/development/plans/freeze_plan_3.6.php

In an offline discussion, Dani and I discussed the possibility of using one
of the Fridays for additional testing to make up for the test days we
removed. For example May 14th could be a test day for those who are
finished with their RC1 contributions. Is this something we should
formalize in the plan, or leave up to the discretion of each component
team? I suspect this would be useful for teams with intensive manual tests
such as SWT, but teams that rely more heavily on automated tests would
probably prefer using that time preparing fixes, writing documentation,
etc. Let me know what you think.

John_______________________________________________