[eclipse-dev] Reminder: 4.13 RC2 on 6th September, 2019

Hi All,

We have 4.13 RC2 scheduled on September 6th , 2019. Please refer to the freeze plan:
https://www.eclipse.org/eclipse/development/plans/freeze_plan_4_13.php
  
Here is the schedule:

September 4 Wed 18:00 EST Release Candidate 2 build
September 5 Thu 1-day test pass against RC2 and sign-off
September 6 Fri Submit RC2 to release train


Please note the following excerpt from the freeze plan:


RC2
Release candidate containing fixes for the majority of known outstanding defects that we intend to fix for 2019-09 (4.13). At the end of RC2 build, there should not be any open defects tagged 4.13. All fixes submitted must have a project lead or PMC vote on the bug report, and the fix must be reviewed by an additional committer (any committer other than the one who made the fix). A positive review from a project lead or PMC member means implicit approval and no vote is needed on the bug report. Ongoing changes to documentation, tests or examples do not require approval.

Thanks & Regards,