We have 4.12 RC2 scheduled on June 7th , 2019. Please refer to the freeze plan:
http://www.eclipse.org/eclipse/development/plans/freeze_plan_4_12.php
  

Here is the schedule:

June 5 Wed 18:00 EST Release Candidate 2 build
June 6 Thu 1-day test pass against RC2 and sign-off
June 7 Fri Submit RC2 to release train

Please note the following excerpt from the freeze plan:

RC2
Release candidate containing fixes for the majority of known outstanding defects that we intend to fix for 2019-06 (4.12). At the end of RC2 build, there should not be any open defects tagged 4.12. All fixes submitted must have a project lead or PMC vote on the bug report, and the fix must be reviewed by an additional committer (any committer other than the one who made the fix). A positive review from a project lead or PMC member means implicit approval and no vote is needed on the bug report. Ongoing changes to documentation, tests or examples do not require approval.

Regards,