Hi Folks,

Earlier today we had an ECF conference call...here is the agenda+meeting notes [1].

The Kepler-relevant highlight: We (ECF) will produce planned release builds for Kepler on May 3, May 10, and May 21. These dates are to meet the desires of the Kepler simultaneous release as expressed by David Williams on [2].

If some unexpected critical bug is identified the needs a build of non-httpclient4 parts of ECF, we will be able to schedule a later ECF build. The httpclient4 contribution will have it's final release build on May 21, however.

Remember to consult our ramp-down policy for timing of all work that's going on [3]

Thanks,

Scott

[1] http://wiki.eclipse.org/ECF_Conference_Call_4.30.2013
[2] https://bugs.eclipse.org/bugs/show_bug.cgi?id=406845
[3] http://wiki.eclipse.org/ECF_Kepler_Ramp-Down_Policy