Hi Harshana, Scott, Markus, and Wim,

Here is the milestone plan for my GSOC project 'Enhancing Salvo Newsreader'

Plan       

M1:Deliver Enhanced notifications for own posts            May 31

M2:Provide developed notification count                        June 6

M3:Deliver developed notification list                            June 17

M4:Linking notification to the relevant article.                June 24

M5:Implement functionality for user defined filters.        July 4

M6:Deliver unread post counter for filters.                     July 10

M7:File system store completion                                  July 28

M8:Enhanced article view                                            August 12

M9:Produce documentation of project                          August 18

M10:Provide NNTP independent Salvo product               Optional

Milestones

M1:Deliver Enhanced notifications for own posts

Completion of this milestone will provide a special notification for users own posts. This notification will be shown in a different color and it will blink.

M2:Provide developed notification count

This milestone will deliver a notification pop-up where it will show the show the number of missed notifications.

M3:Deliver developed notification list 

Completion of this milestone will provide a notification list where notifications will be viewed prioritized by the received time. 

M4:Linking notification to the relevant article.

This milestone will deliver a notification pop-up which will direct user to relevant article when a user click on a notification.

M5:Implement functionality for user defined filters.

Completion of this milestone will provide an option to users to define custom filters in th news digest view so that posts will be grouped into those filters.

M6:Deliver unread post counter for filters.

This milestone will deliver a unread post counter for each user defined filter.

M7:File system store completion

This milestone will deliver a fully functional file system store which includes all the functionality resides in Derby store.

M8:Enhanced article view

Completion of this milestone will deliver a bug free, more stable and user friendly article view.

M9:Produce documentation of project

This milestone will provide complete set of documentation of the project.

M10:Provide NNTP independent Salvo product 

Currently Salvo product depends on NNTP. Completion of this milestone will provide a NNTP independent Salvo product.  


Note: Milestone plan will be updated as the project goes on. I will make the milestone plan available in the project wiki [1] and will do the relevant changes there. Also M10 will be implemented within the GSOC program if the time permits. Else I will look into it personally.


Your comments are valued.

Regards,
Tishan