[e4-dev] Delay M3 by 1 week? response required

With many people coming back off the Christmas break I've had a couple
of requests to delay the M3 milestone by 1 week, to allow the teams to
stabilize their M3 changes.  I'm not against this.

Old: Jan 8th, 2010 [1]
New: Jan 15th, 2010

This will not effect the date of M4, Feb 19th.

So the question is: Do we delay M3 until next week?  As usual, I need
3 +1s and no -1s from the committers.  I'll make a decision by
Tuesday, Jan 5th at 12:00 EST.

Later,
PW

[1] http://wiki.eclipse.org/E4/Builds#Milestone_Builds

-- 
Paul Webster
Hi floor.  Make me a sammich! - GIR