Date Prev][
Date Next][
Thread Prev][
Thread Next][
Date Index][
Thread Index]
[
List Home]
[dsdp-tm-dev] Request to postpone RSE 1.0 by 1 more week - Committers please vote
|
Hello,
I would like to postpone RSE 1.0 by one more week for
the following reasons:
* Testing uncovered some major bugs only recently,
so we still have 3 major bugs open. Even if they
could be fixed today, I'm uncomfortable with
releasing them without additional re-testing.
* EMO Legal still has not approved our about files.
I have confirmation from them that approval should
come today, but I can't wait until late night
with building our release.
* I got the ability to create signed jar files only
recently; waiting another week will allow me to
set up the build processes such that we can provide
a secure, jar-signed RSE 1.0 release
* Waiting for 1 more week gives us the chance to
- test against Eclipse 3.3M3 (which some people
may use)
- fix some additional non-critical but annoying
bugs
- think again about some API changes that we
already have patches for
If committers disagree with postponing, I'd be
creating a 1.0 release instead of RC4 late today.
If committers agree with postponing, the plan for
next week would be as follows:
* Instead of 1.0, release RSE 1.0RC4 today
* Next week, perform an automatic I-build every
night at 6am Ottawa time for testing and verification
* Make sure that ALL CRITICAL BUG FIXES ARE IN by
wednesday evening; keep time for documentation
changes only on thursday and friday
* Release RSE 1.0 on friday.
Committers please vote:
+1 from Martin Oberhuber
Thanks,
--
Martin Oberhuber
Wind River Systems, Inc.
Target Management Project Lead, DSDP PMC Member
http://www.eclipse.org/dsdp/tm