Hi folks,


find below a first schedule that the Eclipse Platform is looking at for the 3.3 (Europa ) train.


If we want to take part with RSE 2.0 in the Europa Coordinated Release next year, we'll be
supposed to follow those milestones approximately (by few weeks off).


We could discuss this in more detail in the TM meeting (first wednesday in August).


Cheers
Martin



*From:* cross-project-issues-dev-bounces@xxxxxxxxxxx [mailto:cross-project-issues-dev-bounces@xxxxxxxxxxx] *On Behalf Of *John Arthorne
*Sent:* Thursday, July 20, 2006 11:20 AM
*To:* Cross project issues
*Subject:* Re: [cross-project-issues-dev] Europa milestones needed




If it helps, the eclipse platform project is tentatively targetting the following dates for the first milestones, following the usual six week rhythm:

       Thursday Aug. 10, 2006 - Milestone 1 (3.3 M1) - stable build
       Friday Sep. 22, 2006 - Milestone 2 (3.3 M2) - stable build
       Friday Nov. 3, 2006 - Milestone 3 (3.3 M3) - stable build
Friday Dec. 15, 2006 - Milestone 4 (3.3 M4) - stable build

These dates will be confirmed when the first draft of the 3.3 plan is released, either at the end of this week or early next week.

       John
<https://dev.eclipse.org/mailman/listinfo/cross-project-issues-dev>

_______________________________________________
dsdp-pmc mailing list
dsdp-pmc@xxxxxxxxxxx
https://dev.eclipse.org/mailman/listinfo/dsdp-pmc


Back to the top