Re: [cross-project-issues-dev] Can we have a slight extension this evening ... plus ...

Yes, that's fine.

Plus, I see some other problems:

1) Being a good citizen, I added "time out if build is stuck" recently, but see I was too optimistic on some of the times (and one was a typo). I have increased the time limits.
2) MPC contribution for Mars.1 RC2  is currently causing Mars build to fail. I mention it here, since I have not gotten "blame mail" for it yet, so originator may not have either?
3) The Neon VALIDATE.gerrit job failed with a very unusual error, so I "cleaned workspace" and re-triggered the build. It ran ok then, so not sure what caused original issue?

Thanks,
 



From:        Jeff Johnston <jjohnstn@xxxxxxxxxx>
To:        Cross project issues <cross-project-issues-dev@xxxxxxxxxxx>,
Date:        09/02/2015 03:39 PM
Subject:        [cross-project-issues-dev] Can we have a slight extension this        evening
Sent by:        cross-project-issues-dev-bounces@xxxxxxxxxxx




Linux Tools is trying to get our RC2 build finished, but it might be tight before 5:00 pm.

Can we have a slight time extension please?  We expect to have it finished.

Thanks,

-- Jeff J.
_______________________________________________
cross-project-issues-dev mailing list
cross-project-issues-dev@xxxxxxxxxxx
To change your delivery options, retrieve your password, or unsubscribe from this list, visit
https://dev.eclipse.org/mailman/listinfo/cross-project-issues-dev




Back to the top